Waterloo looks forward to a new station

Waterloo looks forward to a new station

Works related to the GEN project in the Brussels-Capital Region and the province of Walloon Brabant resumed in autumn 2018, after a three-year hiatus due to budgetary reasons. To make it possible to quadruple line 124 (Waterloo, Eigenbrakel, Nijvel) and carry out the infrastructure works to extend the railway platform on this line north of Waterloo, Waterloo station has recently begun to undergo a major transformation.

The much-discussed GEN project is being managed by TUC RAIL, a division of Infrabel specialising in the construction of new railway infrastructure and the adaptation and modernisation of existing railway infrastructure. Drawing on its experience of earlier GEN projects dating back to 2002, TUC RAIL is responsible in Waterloo for project management, studies relating to railway elements and supervision of all the works, with the exception of the associated NMBS car park. NMBS, in turn, is responsible for redeveloping the station site, the buildings accessible to rail passengers and platform equipment. In other GEN projects, it also undertakes the studies and delivery of the car park and other infrastructure facilities for passengers at and around station sites. To minimise infrastructure works in Waterloo’s densely urbanised station area and meet the stipulated delivery deadlines, Infrabel and NMBS formed a partnership to include the redevelopment of Waterloo station in a public contract, under TUC RAIL’s supervision.

Recentelijk werd geïnvesteerd in een breekinstallatie met een minimale geluidsproductie.

The station will ultimately be built above ground, rather than underground as originally planned.

Modern, comfortable and accessible

The new station must not only meet today’s transport needs, but also anticipate future developments. The original project, which received planning permission in 2010, has been redesigned to improve accessibility for people with reduced mobility and optimise project costs. The new station building will therefore be built above ground, not underground, close to the new NMBS car park and the current station square. “It will be a modern, comfortable complex where everyone feels welcome. Plenty of cycle parking will also be provided at the various entrances to the station site,” says Maxime Mouravieff, NMBS project manager for the GEN stations on line 124. The platform layout is also being changed to two side platforms and one island platform, ensuring a direct connection between the surrounding streets, the station and the platforms. The island platform will only be needed occasionally, specifically in the event of a fault or incident on the railway line.

First phase

Anne-Cécile Roks oversees the budget, schedule and quality of the works entrusted to the main contractor as part of the first phase of the redevelopment of Waterloo station. “This first phase began in August 2019. It includes construction of the new station complex and demolition of the existing building, which will make way for the long-awaited fourth track. The next step is to build a side platform and half of the future island platform, including new access points. A new passageway approximately 6 metres wide will be built beneath the tracks, along with access routes to the platforms, ramps for passengers with reduced mobility and stairs. Finally, the programme includes construction of canopies and cycle parking, and redevelopment of the station area east of the tracks.”

Waterverneveling aan de mengcentrale zorgt op droge dagen dat er geen stofdeeltjes op de sites van de buren terechtkomen.

The new station will be modern, comfortable and accessible.

Second phase

“The second phase of the works will begin once the tracks have been diverted onto the new railway platform,” says Noëlle Hamaide, project manager for the quadrupling of line 124, who is responsible for overall project management, budget monitoring, and project scheduling and phasing. “At that point, the remaining works will begin, including construction of the side platform on the west side and completion of the island platform, as well as redevelopment of the station area west of the tracks. The new station building will open in summer 2020. The first phase of the redevelopment will be completed by the first half of 2021, and the second phase by the end of the second half of 2023.”

TUC RAIL has the capacity to deliver large-scale, phased, multidisciplinary projects. “In Waterloo, the main challenges are the complex works in a densely urbanised area and the diversion of utility services to enable line 124 to be quadrupled, all within the timescale agreed with the federal government and our partners,” explains Noëlle Hamaide.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFuture-proofing roads and railways
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.