General

‘The busiest bridge in the country’ is being renovated

Het voegen gebeurt tijdens speciaal vastgelegde TLO’s (tijdelijke lijnonderbrekingen) van 30 uur.
Het voegen gebeurt tijdens speciaal vastgelegde TLO’s (tijdelijke lijnonderbrekingen) van 30 uur.

In autumn 2020, Renotec began renovating the railway bridge over the Brussels Ring in Zaventem. As many as 160,000 cars pass beneath it on weekdays. “That immediately makes it one of our most visible construction sites,” says Tim Sneyers, project manager at the civil engineering division.

Renotec’s concrete renovation division began work on the renewal of the railway bridge over the Brussels Ring in Zaventem, on behalf of Infrabel. Tim Sneyers: “It is a large railway bridge, about 170 m long. In terms of both rail traffic over the bridge and road traffic underneath it, this is one of Belgium’s busiest intersections. Around 450 trains and as many as 160,000 vehicles pass through on a weekday. The long railway bridge was built in the 1970s and has five piers supporting six spans with a concrete deck.”

A few months ago, Renotec began renovating the railway bridge over the Brussels Ring in Zaventem.

Essential renovation

The 50-year-old bridge was showing signs of wear, so concrete repairs were necessary. Renotec is renovating both the superstructure, where the waterproof joints beneath the tracks are being replaced, and the substructure, where 108 bearings are being replaced and the concrete repaired. Tim Sneyers: “The bearings are the supports between the bridge decks and the piers. To jack up the bridge at these bearings, we have to lift it a few millimetres. This was quite a complex operation. Jacking over the Brussels Ring, with trains running above, is no easy task. The bridge is jacked up at night, when there is no rail traffic. 

Time was not the only challenge. There was also a lack of space for jacking. Tim Sneyers: “We need space to install the jacks themselves, but there wasn’t any, mainly because of the limited space on top of the bridge piers in the existing situation. For every jack we installed, we built a concrete corbel against the bridge pier. There are 90 corbels in total, ranging in height from 70 cm to 100 cm, depending on their position and the forces they have to bear. Replacing the bearings is a relatively small intervention, but the preparation made the work challenging in this case.”

Renotec is renovating both the superstructure and the substructure, where the bearings are being replaced and the concrete repaired.

Concrete repairs

The first phase of jacking and bearing replacement has now been completed, and phase two began in February. Concrete renovation work is continuing throughout the project. Tim Sneyers: “We subcontract the specific jacking work, while our own people are busy repairing the deteriorated concrete. This kind of renovation is one of Renotec’s key strengths, backed by its BCCA certification.”

According to the schedule, the concrete renovation work, phase two of the jacking work and replacement of the waterproof joints on the bridge deck are due to be completed in May. Tim Sneyers: “The joints are replaced during specially scheduled 30-hour TLOs (temporary line closures). As international services also use these lines, these periods when the line is out of service are scheduled well in advance. During each closure, the tracks and ballast are removed so that the bridge joint can be replaced.”

Minimal disruption

It is very important to Renotec that the renovation work causes as little disruption as possible to passers-by and local residents. Tim Sneyers: “That is why, as with the renovation of the railway tunnel in Ensival, we are also minimising the impact on rail traffic here. Passengers can rest assured. The impact on motorway traffic is also minimal. Traffic can continue to pass during the works. If, in an exceptional case, a lane does have to be closed, this will be done at night.”     

Een zakelijke vraag aan BCCA? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
  • CompanyBCCA
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.