Successful dewatering and recharge for the construction of a rotary car park in Bruges

Successful dewatering and recharge for the construction of a rotary car park in Bruges

A new underground rotary car park with 139 spaces and 66 private garages is currently being built in the centre of Bruges. The project, with Europroject and VDD Project Development as clients, consists of two underground levels. Specialist contractor G. Smeyers has been appointed to carry out the dewatering works. “Dewatering is now operational and the excavation has been pumped dry to the required depth,” says René Lambrechts, managing director of G. Smeyers nv..

The rotary car park will later be operated as a public car park by Interparking. VDD Development Project is taking over part of the car park for use as a private car park for its future Weyler­kazerne project. Building an underground car park measuring approximately 72 x 60 lm, to a depth of 7 m below existing ground level, in the heart of Bruges’ historic centre, is no easy task. “The resting groundwater level is shallow, at 90 cm below ground level, and the subsoil on site contains a significant settlement-sensitive layer,” says René Lambrechts of G. Smeyers. “Dewatering an excavation of this size to a depth of 7 m is therefore not without risk.”

img_20200212_165031-kopieren

Specialist contractor G. Smeyers has been appointed to carry out the dewatering works for the construction of a rotary car park in the centre of Bruges.

Further investigation

In the first phase, G. Smeyers carried out an initial dewatering study based on a 3D model, using the available data from cone penetration tests carried out on site. René Lambrechts says: “It soon became clear that the impact of dewatering on the surrounding area would be too great and could cause unacceptable settlement if an open excavation were used. Additional protective measures therefore had to be devised. Following consultation between all parties, it was agreed to carry out further ground investigations, comprising four exploratory boreholes to a depth of 14 m, with disturbed samples taken and permeability tests carried out at depths of 13 to 14 m. We were specifically looking for a potential low-permeability layer.”

A new dewatering study was carried out in the second phase, this time incorporating a low-permeability wall and recharge wells outside the excavation. “The wall depth was optimised using the 3D model and set at 16 m below ground level,” explains René Lambrechts. “This made it possible to install recharge wells just behind the low-permeability wall. The excavation is being dewatered using a combination of vertical wellpoints and vacuum deep wells within the excavation, in layer 3 (dense sand with sandstone bands, water-bearing). However, this water becomes aerated during pumping and is therefore unsuitable for recharging through the recharge wells. Once the excavation has been dug to a depth of 7 m, tieback anchors will need to be installed from its base. These extend below the bottom of the low-permeability wall into layer 5 (dense sand with sandstone bands, water-bearing). This meant that pressure relief dewatering was also required in layer 5.”

img_20200206_102132-kopieren

The specified dewatering system is achieving the required groundwater level inside the excavation without any problems.

Continuous monitoring

The water from the pressure relief dewatering could be pumped without aeration and is ideally suited to supplying the recharge wells. This keeps the water level in layer 2 (clay interspersed with thin sand layers, a low-permeability layer) stable, preventing settlement in the surrounding area. René Lambrechts says: “Finally, in layer 1 (silty sand, water-bearing), short vacuum wellpoints outside the excavation are used to keep the water level as low as possible and limit water pressure on the soilmix wall. The whole system is continuously monitored using piezometers inside and outside the excavation, fitted with divers that continuously record the water level. All parties involved can access these readings online.”

modeloutput-kopieren

Model output.

Reference project

At the client’s request, G. Smeyers’ team submitted the dewatering permit application through the environmental permit portal, with the dewatering study forming a key part of the application. A discharge permit was also applied for from Aquafin. “Dewatering is now operational and the excavation has been pumped dry to the required depth. The specified system is achieving the required groundwater level inside the excavation without any problems. The recharge system is also performing as expected, and the actual pumping rates are closely in line with those predicted by our dewatering study. The Rotary car park project is an important reference for G. Smeyers. The company has made a significant contribution to delivering the project, both during the permitting phase and throughout construction,” concludes René Lambrechts.      

Een zakelijke vraag aan Smeyers nv? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
  • CompanySmeyers nv
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.