Refurbished Scheldt Bridge ready for the future

Sinds maart vorig jaar werkte de tijdelijke maatschap Colas – Renotec, in opdracht van het Agentschap Wegen & Verkeer, aan de grondige renovatie.
Sinds maart vorig jaar werkte de tijdelijke maatschap Colas – Renotec, in opdracht van het Agentschap Wegen & Verkeer, aan de grondige renovatie.

On Saturday 4 December 2021, the refurbished Scheldt Bridge in Dendermonde reopened to all traffic. Since March last year, the temporary joint venture Colas, Renotec had been carrying out a major refurbishment on behalf of the Agentschap Wegen & Verkeer. Only the bridge’s structure was retained. “It was a great project, and one we look back on with great satisfaction. The bridge opened to traffic at the end of last year without a hitch,” says Kevin Van Haezendonck, project manager at Colas.

Overnight from 3 to 4 December, all traffic signs were removed so that traffic could use the bridge from 4 December. “With these works completed, the Agentschap Wegen en Verkeer has carried out major refurbishments on 5 bridges in East Flanders this year. These investments are part of my comprehensive approach to renovating and modernising civil engineering structures (bridges, tunnels and retaining walls) in Flanders. We will continue and step up our investment in bridge refurbishment in the years ahead,” Flemish Minister for Mobility and Public Works Lydia Peeters said in December.

While Renotec carried out the specialist refurbishment work, Colas was responsible for a large proportion of the demolition work, all traffic management and the asphalt works.

Complete refurbishment

The refurbishment has completely renewed the bridge over the Scheldt in Dendermonde: the road surface, parapets, lighting and concrete safety barriers. The bridge’s waterproofing was also entirely replaced, and concrete repairs were carried out on its underside. Infrastructure specialist Colas worked with refurbishment specialist Renotec to deliver the project. Kevin Van Haezendonck says: “The bridge was completely refurbished, with only the structure retained. The reinforcement in the exposed concrete structure was fully inspected and given a protective coating where necessary. An epoxy scratch coat, new waterproofing and new bridge deck joints were also installed. After the poured asphalt layer was laid, the bridge was finished with the asphalt surfacing, new linear elements, cast-in-place New Jerseys and a new central safety barrier. The drainage beneath the bridge was also renewed, as was the existing parapet. Those are the main works that were carried out.”

The refurbishment has completely renewed the bridge over the Scheldt in Dendermonde: the road surface, parapets, lighting and concrete safety barriers.

While Renotec carried out the specialist refurbishment work, Colas was responsible for a large proportion of the demolition work, all traffic management and the asphalt works. Kevin Van Haezendonck says: “We demolished the bridge down to the waterproofing. Colas also led the phasing of all traffic signs and road markings, working with our north-east division. After the demolition, we reviewed the bridge design with Renotec and the Agentschap Wegen & Verkeer. We looked at the approaches at both ends of the bridge, and it was also important to minimise the thickness of the levelling layer to save costs. The design was optimised, after which Renotec could begin the repairs and Colas could then start the asphalt works. The asphalt was laid using a guide wire so that we could achieve the minimum thickness throughout.”

Working together

Clear planning and collaboration between all parties were crucial to bringing the project to a successful conclusion. “And that went very well,” says Kevin Van Haezendonck. “The bridge opened to traffic in early December last year without a hitch or any comments. We also renewed the upstands along the cycle paths. That was not originally included in the plan, but the Agentschap Wegen & Verkeer requested it later on. Our work is now fully complete, but Renotec is currently putting the finishing touches to the concrete repairs beneath the bridge. We look back on this project with great satisfaction. Colas’s strengths came through very clearly, and the Colas Group’s vertical integration and diversification proved particularly valuable. This applied to both the traffic management and the concrete works, as we were able to draw on the expertise of our north-east division for both.”

On Saturday 4 December 2021, the refurbished Scheldt Bridge in Dendermonde reopened to all traffic.

Bridge refurbishment action plan

Minister Peeters aims to tackle the historic maintenance backlog affecting civil engineering structures and is investing heavily in refurbishment, maintenance and modernisation between 2020 and 2023. To address the backlog efficiently, Minister Peeters is following a 2020-2030 action plan: “Many bridges in Flanders date from the 1960s and 1970s and need to be refurbished or replaced. With the refurbishment of the Scheldt Bridge in Dendermonde, the agency will have refurbished a total of 5 bridges in East Flanders: 2 over the E17, the Gentbrugge viaduct on the E17, and the 2 major bridges over the Scheldt (Destelbergen and Dendermonde).     

Question about this story? Ask your question

Wie aan Scheldebrug werkte

  1. renovatiespecialistRenotecIn this story
  2. asfaltwerkenColasMentioned in Safety was paramount during Scheldebrug renovation
  3. clientAVW Oost-VlaanderenMentioned in Safety was paramount during Scheldebrug renovation

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectScheldebrug
  • SubjectGeneral
  • CompanyRenotec
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.