Preserving the historic character in the sustainable upgrade of Fort Liefkenshoek

Text Niels RouvroisImage Witteveen+Bos

De parking wordt via een nieuwe voetgangersbrug over de walgracht verbonden met het horecapunt en via een wandelpad langs de westelijke zijde van de omwalling ook verbonden met de aanmeerplaats van de waterbus aan de andere kant van het fort.
De parking wordt via een nieuwe voetgangersbrug over de walgracht verbonden met het horecapunt en via een wandelpad langs de westelijke zijde van de omwalling ook verbonden met de aanmeerplaats van de waterbus aan de andere kant van het fort.

Work on Fort Liefkenshoek, one of the Waasland region’s tourist attractions, is now in its final phase. The project had two aims: to restore the historic ramparts of the old military fort in Kallo to their original condition, and to improve access to the fort with a new pedestrian bridge and car and coach park. Main contractor Soga carried out the work on behalf of the municipality of Beveren, with the design by Cluster Landscapes. Consultancy and engineering firm Witteveen+Bos was responsible for the studies.

At the heart of the Waaslandhaven, right next to the Scheldt and close to a De Waterbus stop, Fort Liefkenshoek is increasingly serving as a gateway to the Waaslandhaven and the surrounding area. Better access was therefore needed. Work began on the outer ramparts, followed by the pedestrian bridge and construction of the new car park. A new access road to the car park will eventually be built via the future Sigmadijk to the south of the fort. The car park will be linked to the hospitality venue by a new pedestrian bridge over the moat, and to the De Waterbus landing on the other side of the fort by a footpath along the western side of the ramparts.

Witteveen+Bos became involved in the project through architect Cluster Landscapes. “That was about two years ago. There was already a preliminary design and a permit in place for us to build on,” says project leader Bart Jansen. “We then developed the scheme through to tender and construction. We were brought up to speed on the project’s background, but there was still a great deal of design and study work to do on the car park, ramparts and bridge. The project is a good example of a multidisciplinary undertaking, something Witteveen+Bos focuses strongly on. The bridge was installed at the end of September, and the entire project is due to be completed by the end of the year.”

For construction and transport reasons, as well as sustainability, the bridge was built in three separate sections

Working together

Working with the architect to reach a shared design consensus was an important factor in this project. Witteveen+Bos project engineer Yarn Cools says: “It is a challenge we are happy to take on, because we are not only very skilled at it, but also have extensive experience. Looking for viable solutions and alternatives, and clearly feeding these back to the architect … that is how you arrive at a design everyone agrees on. Naturally, the architect pays close attention to aesthetics. The architect wanted to create an architectural bridge inspired by a Bailey bridge. This type of bridge was originally used for military purposes, making it a fitting link to the fort. But the design also has to be technically feasible, and a bridge has to meet certain requirements. The bridge was narrow, but the spans were relatively long. For construction and transport reasons, as well as sustainability, it was therefore decided to build it in three separate sections.”

Work on Fort Liefkenshoek, one of the Waasland region’s tourist attractions, is now in its final phase.

Sustainability principles

Sustainability is a top priority for Witteveen+Bos on every project. Particular attention was paid to integrating this project into its surroundings and protecting the existing natural environment. Project engineer Nathan Dutoit says: “For example, no additional trees or lamp posts were installed, to prevent birds of prey from nesting here and threatening local wildlife. There is also a strong focus on infiltration. The car park and fire access road are surfaced with grass concrete pavers on free-draining lean concrete, while the footpath has a semi-bound porphyry surface on an unbound crushed-stone sub-base. The bus lane is the only fully paved area, and there is ample opportunity for water to drain into the surrounding unpaved areas. To limit soil transport and the associated CO2 emissions, the design levels were chosen to achieve a zero balance. This means that raising and filling are carried out using soil excavated on site.” 

Designing the bridge in 3 separate sections also had a positive impact on sustainability. Nathan Dutoit says: “This has transport benefits, but also creates opportunities for circularity in the future, such as dismantling and reusing the sections at another location. Provision has also been made for ducting for electric vehicle charging points. The infrastructure is designed to allow the number of charging points to be expanded systematically as demand for electrification grows. Fort Liefkenshoek is therefore fully prepared for the future.”

Design to cost

By identifying investment costs at an early stage, the team was able to deliver a design within the client’s budget, the municipality of Beveren. Witteveen+Bos has an extensive, up-to-date cost database, enabling construction costs to be estimated accurately. “Other costs, such as risk costs, can also be budgeted for. Witteveen+Bos can use the SSK methodology for this, which originated in the Netherlands,” concludes Bart Jansen.      ■

Question about this story? Ask your question

Who worked on it

Fort Liefkenshoek in Beveren-Kruibeke-Zwijndrecht

  1. main contractorSoga
  2. architectCluster Landscapes
  3. consultancy and engineering firmWitteveen+Bos
  4. municipalityBeveren

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectFort Liefkenshoek
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
  • CompanySoga
  • CompanyCluster Landscapes
  • CompanyWitteveen+Bos
  • CompanyBeveren
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.