Renovation work on the Westerstaketsel in Ostend began in October 2017. The first phase of the work, treating the head of the breakwater, was completed before the start of last summer, and renovation of the main section is now also under way. At 650 metres, the breakwater in Ostend is one of the longest in the world. “The breakwater is not being completely renewed. A large part of the superstructure and the planks are being reused,” says Xavier Van Huele, managing director of main contractor NV Van Huele.

The Flemish government owns the historic heritage site, and the renovation work is therefore being carried out on behalf of the Maritime Access division of the Department of Mobility and Public Works. The temporary partnership Van Huele-Soetaert is the contractor, and around 7 million euros is being invested in the overall renovation. “After the first phase, the breakwater was reopened to the public over the summer. For the first time in years, visitors could reach its furthest point again. When phase two began in October, the breakwater was closed once more,” says Xavier Van Huele.

Westerstaketsel

The critical joints beneath the plank floor are being reinforced with timber and metal connections.

Renewing versus preserving
Starting at the head of the breakwater, Van Huele-Soetaert is working backwards towards the shore. The tropical hardwood used to build the structure is being carefully inspected and analysed. From floorboards and piles to knee braces, support beams and railings, damaged sections are marked and replaced, while sound sections are retained. Xavier Van Huele: “The breakwater is therefore not being completely renewed. A large part of the superstructure and the planks are being documented and reused. At the government’s request, and with sustainability in mind, we are retaining as much of the original material as possible, so that nothing is lost.”

Westerstaketsel

Starting at the head of the breakwater, Van Huele-Soetaert is working backwards towards the shore.

Epoxy
The critical joints beneath the plank floor are being reinforced with timber and metal connections. Where possible, the end grain is being sealed with epoxy to prevent further deterioration. “Everything is also being repainted and coated,” says Van Huele.
“The name says it all: tropical hardwood is hard, so it is not easy to work with. Its high density also makes it very heavy, and working it requires the right knowledge and experience. On the other hand, tropical hardwood is a very rewarding material thanks to its durability.”

Westerstaketsel

Damaged sections are marked and replaced, while sound sections are retained.

Logistical challenge
Stability studies showed that heavy loads on the superstructure cause deformation and damage to the breakwater. As a result, the contractor cannot use large machinery. The project therefore presents a considerable logistical challenge. Van Huele: “The work is a logistical challenge. At the points where we cut an opening for a new pile, we can no longer get through. Planning is therefore crucial. We are working at five locations at once, moving from back to front at each one. The short time available to complete the work is also a challenge. Normally, a crew can replace around 100 m3 in a year, whereas here we are talking about approximately 400 m3 in a year.”

End of May
Despite the time pressure, the work is still on schedule for now, and the breakwater is due to reopen to Ostend and its visitors at the end of May. “We are doing our best to stick to the schedule, and that is going quite well. Above all, we aim to deliver work of a high standard and quality, whether it is a small project or a large one like this,” concludes Van Huele.   

Question about this story? Ask your question

Wie aan Westerstaketsel werkte

  1. main contractorNV Van HueleIn this story
  2. contractorVan Huele-SoetaertIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWesterstaketsel
  • SubjectGeneral
  • CompanyNV Van Huele
  • CompanyVan Huele-Soetaert
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.