No new slab track without a 3D scan in the Sint-Lambertustunnel in Liège

No new slab track without a 3D scan in the Sint-Lambertustunnel in Liège

The Sint-Lambertustunnel at the station of the same name in Liège is getting new slab track. Precise installation is even more important for this type of track than for conventional rails, as slab track is cast in concrete, making subsequent adjustments impossible. To ensure the train’s clearance envelope, Landmeetkunde Duyck mapped the tunnel in detail using a 360° 3D scan.

Landmeetkunde Duyck was also involved last year in the first phase of track renewal in the Sint-Lambertustunnel. “We began by setting out all the reference points in the tunnel and surveying the existing track. Our measurements were used to optimise the designs for the new track layout,” explains managing director Pieter Duyck. “We also carried out a 3D scan of the entire tunnel, which is just under a kilometre long, to ensure the train’s clearance envelope. It goes without saying that the train must not collide with anything as it passes through the tunnel.”

Preparation is everything

In the Sint-Lambertustunnel, main contractor MOBIX is installing new slab track. This type of track is not laid on ballast, but cast into concrete. That means no adjustments can be made once the track has been installed. Thorough preparation is therefore crucial, and Landmeetkunde Duyck plays a vital role in this. “Our job is to survey everything to millimetre accuracy,” stresses Pieter Duyck. “After the initial 3D scan, we assist with positioning the track so that it is perfectly aligned. Before the concrete is poured, we return to the site twice to check that no changes have been made during the other works in the tunnel. Once the track has been installed, we also check it against our 3D scan before a train passes through the tunnel.”

foto1-kopieren

The 3D scan is carried out using a Trimble TX8, a scanner that can scan the entire tunnel in one day.

The 3D scan is carried out using a Trimble TX8, a scanner that can scan the entire tunnel in one day. “This surveying instrument allows us to collect a wealth of data about the tunnel and the condition of the track,” says Pieter Duyck. “Specialist software lets us virtually run a train through the tunnel to identify any danger zones in the designs.”

A wealth of experience

The surveys were carried out on the very busy railway line L34: Liège Guillemins. To minimise disruption from temporary line closures, the work is being carried out during the summer holidays. “We have to work to a very tight deadline, but fortunately we have specialist surveyors and the equipment needed to deliver projects like this successfully,” says Pieter Duyck. “Slab track is rare in Belgium, so a project like the Sint-Lambertustunnel is a great challenge for us. We now have the necessary expertise thanks to our experience in the Liefkenshoektunnel in Antwerp and the Schumantunnel in Brussels, where we also carried out 3D scans as part of projects to install new slab track. On railway projects, you need to be flexible and have people with the right expertise. Landmeetkunde Duyck has now been active in railway works for nine years, so we are no strangers to this kind of work.”     

Een zakelijke vraag aan MOBIX? Get in touch

Who worked on it

Sint-Lambertustunnel in Luik

  1. main contractorMOBIX
  2. 3D-scanLandmeetkunde Duyck

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSint-Lambertustunnel
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
  • CompanyMOBIX
  • CompanyLandmeetkunde Duyck
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.