New tram tracks at Harmoniepark completed at speed

At the beginning of May, De Lijn began renewing the tram tracks at Harmoniepark in Antwerp. Barely two weeks later, trams were running again. It was a remarkable project, expertly managed by experienced rail contractor Frateur, De Pourcq. “We were only able to pull off this remarkable feat thanks to the tremendous efforts of everyone involved,” says Jan Gillis, technical director at Frateur, De Pourcq.
The tram tracks and road surface at the junction of Mechelsesteenweg and Belgiëlei were renewed to improve safety for road users and passengers. Jan Gillis: “The work involved renewing five sets of points, two crossings and around 300 m of track. Around four tram lines pass through here, connecting both Hoboken and Mortsel with the left bank. It is therefore an exceptionally busy location, not only for trams but also for cars. Combined with the scale of the work, this made it a particularly challenging project. A completely new layout of points and crossings had to be installed in a new location.”

Trams were running again just two weeks after work began.
The work was originally scheduled to take place during the Easter holidays. “We were due to start the day after the Tour of Flanders and finish on Easter Monday,” says Jan Gillis. “We had started the preparatory work, but COVID-19 put a stop to our plans. Our suppliers could no longer deliver, and in mid-March we also put our work on hold. Thanks to the intensive efforts of our prevention department, we were able to get back to work on 22 April. Given the complexity of this project, we immediately contacted De Lijn. With tram and car traffic reduced because of COVID-19, it seemed like a suitable time to tackle the project. We took the initiative ourselves and also contacted the city of Antwerp.”

Thanks to the efforts of everyone involved, this remarkable feat was brought to a successful conclusion.
Extra time pressure
The pieces of the puzzle were almost in place, but then came the news that schools could reopen on 15 May. Jan Gillis: “That added extra time pressure. It was already the end of April, and the work had to be completed by 15 May at the latest. By moving very quickly, we were able to start at the beginning of May. De Lijn’s efforts also deserve credit. Arranging a tram service suspension and replacement bus service normally takes around six months, but for this project it was organised in record time. Meanwhile, we had also contacted around 50 suppliers and subcontractors and asked them to get organised within a week and a half.”
As soon as the green light was given, Frateur: De Pourcq got to work. Jan Gillis: “We deployed a full site team on the project. Our staff were willing to work in shifts around the clock, 24 hours a day, 24/24, including weekends and public holidays. This was no easy task, as we also had to take account of the COVID-19 safety measures. Thanks to the tremendous efforts of everyone involved, we were able to bring this remarkable feat to a successful conclusion. Apart from a few minor problems, everything went very smoothly, and trams were running again on 15 May. We continued working until the beginning of June to complete the road surfacing.”

It was a remarkable project, expertly managed by experienced rail contractor Frateur, De Pourcq.
Experience and expertise
Frateur: De Pourcq has extensive experience working for De Lijn, particularly in the regions of Antwerp, Brussels, Ghent and the coast. That experience was crucial on this exceptional project. “We have a good understanding of the problems that may arise, not only with the tracks but also with overhead lines, point control and other factors, such as underground cables for traffic light control systems. Our experience and expertise enable us to deliver this kind of complex project to a high standard within a very short timeframe,” concludes Jan Gillis.