Infrabel gradually resumes its worksites

Infrabel gradually resumes its worksites

Infrastructure manager solves complex “worksite puzzle” in consultation with its customers to safeguard crucial rail projects

As society gradually gets back up and running, Infrabel and its subsidiary TUC RAIL are also restarting their worksites, step by step. The coronavirus crisis brought all non-essential works to a halt. But thanks to close cooperation between the infrastructure manager and its customers, the various rail operators active in Belgium, a series of major rail projects have been able to restart or be rescheduled, in compliance with the National Security Council’s rules. The infrastructure manager also consulted actively with its various contractors to organise this restart in the safest possible way. This good cooperation will help make up much of the ground lost.

wisselvernieuwing_station-mechelen_2-kopieren

Close cooperation with customers and contractors

Over the past weeks and months, the coronavirus crisis has irrevocably brought most railway worksites to a standstill. But behind the scenes, rail specialists have been busy. In consultation between Infrabel, the rail operators and its contractors, a meticulously devised plan took shape to make up as much of the lost ground as possible during the second half of 2020. This involves restarting or rescheduling various strategic rail projects. Work will also continue during the construction holiday. Naturally, all safety and social distancing requirements will be observed. This new schedule will prevent a domino effect of negative consequences, including impacts on rail safety and punctuality, delays to multiple projects and sharply rising costs, while also avoiding a flood of worksites in 2021.

wisselvernieuwing_station-mechelen_3-kopieren

Pieces of the puzzle fall into place

Since the schedule for many works follows a logical sequence and phasing, it is not possible to postpone the work that has not been carried out for a long time. Projects often planned months, and sometimes years, in advance now have to be reorganised at very short notice. Train services and replacement buses must also be coordinated with the works. This is a huge challenge. It can only be met through close cooperation between Infrabel and its customers, the rail operators, who must solve this complex puzzle together during the coronavirus crisis. This year, 3 planned projects are closely interlinked and must be carried out in a specific order. If this proves impossible, other projects will be delayed by years.

-Puzzle piece 1: Tunnel T + new rail junction in Schaarbeek

Specifically, from 30 May to 3 July 2020 and from 1 August to 12 October, Infrabel will build a new rail connection and junction on the Schaarbeek-Vorming site, enabling freight trains from Antwerp to connect to the eastern ring line around Brussels. These are the works on the so-called “Bruulstraat” rail junction and “Tunnel T”. By postponing these works by more than a month, space is freed up in the schedule to renew the Jan Bogaertsbrug and the railway line between Mechelen and Dendermonde (L53). The Tunnel T and L53 works cannot be carried out at the same time, because during the works in Schaarbeek this railway line will serve as one of the possible diversion routes for train traffic.

-Puzzle piece 2: Renewal of the Jan Bogaertsbrug bridges and Mechelen-Dendermonde railway line

The Jan Bogaertsbrug bridges in Kapelle-op-Den Bos are at the heart of the rail works. Most of the bridges’ electromechanical equipment has reached the end of its service life and urgently needs modernising. Some of the work on the railway bridge was already under way. The rest of the bridge was due to be completed during the Easter holidays. Under the new schedule, work will now take place from 4 July to 26 July inclusive. To carry this out safely, the line must be closed completely, meaning no trains can run on the Mechelen-Dendermonde railway line (L53). The infrastructure manager is taking the opportunity to carry out other essential renewals along the entire line at the same time, including rails, sleepers and ballast. The L53 runs through Mechelen station. One major project here is the renewal of the points at the station exit. If Infrabel does not carry this out, the commissioning of the rail bypass in Mechelen will be at risk.

-Puzzle piece 3: Rail bypass and Mechelen station

The rail bypass is a new railway line just over 3km long, running behind Mechelen station. This new connection provides additional capacity, allowing trains to pass through the station faster. It also completes Belgium’s high-speed rail network.

But before this bypass can be completed, other rail works still need to be carried out in and around the station. These include renewing points, tracks, overhead lines and signals. Crucially, the Mechelen-Dendermonde railway line (L53) must connect to the Antwerp-Brussels railway line (L27) at the station to ensure sufficient capacity for trains. Preparatory work is scheduled for the weekends of 16+17 May and 23+24 May. Work will also continue during the weeknights of 25, 26, 27 and 28 May, as well as the nights of 2, 3, 4 and 8, 9, 10 and 11 June 2020.

Commissioning the bypass is also a necessary condition for continuing work on the entire Mechelen station project. How exactly does this work? Mechelen station is an important station. During the station works, sufficient track capacity must always be available for trains to run. To avoid cancellations and maintain punctuality, 10 tracks are therefore always needed. When the first two tracks, 9 and 10, are taken out of service in phases, two other tracks are needed to make up for the loss of capacity. These are the bypass tracks, 11 and 12. This allows the works to progress without losing the capacity required.

wisselvernieuwing_station-mechelen_4-kopieren

Alternatives for train services

The works will disrupt train services, affecting both passenger and freight trains. Freight trains will be diverted. For alternatives for passenger services, including replacement buses, please refer to the passenger information on our colleagues at NMBS’s website and app.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFuture-proofing roads and railways
  • SubjectGeneral
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.