Greater attention to groundwater pumping on infrastructure projects

Griet Goossens
Griet Goossens

Will we see news reports again this summer about prolonged drought, insufficient rainfall and falling groundwater levels? Will there be another call to use water sparingly? In the summers of 2019, 2020 and 2022, we repeatedly saw critical posts from members of the public on social media about dewatering: “But here in my street, they’ve been pumping water out and discharging it into the sewer for months, while I’m supposed to use water sparingly. Someone should do something about that.” 

Attention to groundwater pumping during construction work has increased significantly in recent years. Regulations have been tightened. A certification scheme for drilling companies has been introduced, together with training requirements and reporting obligations. Guidelines for dewatering have been drawn up. Additional requirements have been introduced for flow meters on construction sites. The dewatering hierarchy is being enforced ever more strictly. Its priority is to limit the volumes pumped by using water-level-controlled dewatering and by returning and infiltrating the water. Next comes the beneficial use of dewatering water, followed by discharge into surface waters such as streams and ditches. Discharge into the sewer is permitted only as the final step in the hierarchy.

Applying for and obtaining an environmental permit (Class 1 or 2) or a notification (Class 3) for dewatering is considered complex and time-consuming. Ever stricter special conditions are being imposed. Recent case law also indicates that assessing the environmental effects of dewatering must form part of the study into the overall environmental impact of the entire project.

The impact of dewatering on the surrounding area

Lowering the groundwater table is only one aspect of the impact of dewatering on the surrounding area. The mobilisation of contaminants from nearby polluted land must also be prevented. Remediated sites must also be investigated further, as residual contamination is a real possibility. Treating pumped groundwater is no longer unusual. The PFAS issue has also led to growing awareness in this area.

The impact on nature reserves, forests and parks is also assessed in each case. Is there a risk that tree roots will no longer be able to absorb water? Is there a risk that the soil will dry out? Irrigation of nature reserves, as well as of valuable trees, is increasingly being considered.

Salinisation, whereby the salt content of the soil and groundwater increases, is a key concern in coastal and polder areas. The mixing of fresh and saline groundwater must be avoided at all costs.

The risk of settlement affecting nearby buildings has been assessed for some time. Several cases of damage are known. The presence of peat or other soft layers, fill soils and heterogeneous foundations beneath nearby buildings are all factors that play a part.

The importance of preliminary investigations

Clients commissioning infrastructure projects, such as road and sewer authorities, can no longer simply leave the dewatering investigation, permit application and execution to the contractor and drilling company. The increasing complexity of the regulations, recent case law, the need to limit impacts on the surrounding area and the additional focus on the quality of dewatering water mean that the infrastructure project’s design phase must be expanded to include a dewatering study. This involves a desk study of potential factors in the surrounding area, supplemented by site investigations using deeper electrical cone penetration tests to establish the sequence of sand and clay layers and determine whether peat is present. Preliminary analysis of groundwater quality by an accredited laboratory is also recommended, so that it can be determined whether water treatment is required. 

On the basis of these investigations, a specialist consultancy can develop a dewatering plan tailored to the infrastructure project. If necessary, a certified soil remediation expert can be brought in to assess the risk of mobilising contaminants, or an arboricultural expert to protect old, valuable trees in the surrounding area. This dewatering plan forms the basis for a robust environmental permit application. 

At the same time, more extensive preliminary investigations carried out by the client lead to better tenders and clearer specifications. This enables the contractor to produce a more focused and accurate cost estimate and avoid unforeseen costs. Last but not least, thorough preparation allows the contractor and drilling company to start work on time.   

Griet Goossens
Environment & Climate Adviser, Embuild

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUsing and protecting the subsurface
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.