First phase of new Kuringen railway bridge nearly complete

First phase of new Kuringen railway bridge nearly complete

Raising the clearance height and widening the clearance width: with these two straightforward measures, De Vlaamse Waterweg aims to make all bridges over the Albert Canal more accessible to container ships. If all goes according to plan, the new, higher arch bridge in Kuringen will be launched into place this spring.

In economic terms, the Albert Canal is perhaps the most important waterway in Flanders: around 40 million tonnes of goods are transported along it every year. Yet larger cargo vessels cannot currently use it, as the bridges over the canal are too low in many places. De Vlaamse Waterweg therefore aims to increase the Albert Canal’s capacity by raising every bridge and widening the canal beneath them. The railway bridge in Kuringen is part of this programme: the old bridge, which actually consists of two separate railway bridges side by side, will soon make way for a single impressive arch bridge.

herbosch-kiere-foto-2-kopieren

A temporary sheet-pile wall was installed between the two old bridges to allow construction of the new abutments.

2 metres higher, 36 metres wider

Contractor Herbosch-Kiere, together with Jan De Nul, is responsible for all the civil engineering works involved in building the new railway bridge. Gary Van Gulck, site manager at Herbosch-Kiere: “The new bridge will be 2 m higher than the two old bridges, while the canal beneath it will be 36 m wider. This means that changes have to be made in many places. Our scope of work therefore comprises several elements: piling works to widen the canal, earthworks to raise the railway embankment, construction of new concrete abutments and culverts, and installation of a temporary sheet-pile wall to retain one of the existing bridges …
The cooperation with Jan De Nul is proving very useful. Their expertise in earthworks complements our knowledge of water engineering perfectly.”

Phased works

Work on the bridge in Kuringen began in April last year, and the first phase is nearly complete a year later: “To minimise the impact on the surrounding area and rail traffic, the work was divided into 2 phases. During the first phase, the eastern canal bridge was demolished, along with part of the old culverts. While we built the new abutments and culverts, our partner Victor Buyck worked on the steel structure of the arch bridge. The steel arch structure can be launched into place shortly, after which, in the second phase, we can also demolish the western bridge and Strukton can finalise the track works. In this phase, we will also provide a new cycle and pedestrian tunnel, replacing the old level crossing near Vilstraat.”

herbosch-kiere-foto-3-kopieren

One of the new culverts, with the old culvert behind it. The divided passage for traffic will be replaced by a single, spacious passage.

Train services on a single track

Train services between Hasselt and Kiewit will not be diverted during the works, but will continue to run across a single track on the bridge throughout the project. Gary Van Gulck: “This is, of course, a key consideration and a challenge. The new abutment is right alongside the existing track, as is all the formwork. All formwork operations therefore take place next to a track that remains in service. This requires careful preparation: for example, our tower cranes are configured so that they cannot swing over a passing train under any circumstances. Clear communication with subcontractors is also essential, so that everyone knows the track is in service and wears the required safety equipment.”

A remarkable project

For Herbosch-Kiere, replacing the railway bridge in Kuringen is certainly no ordinary assignment: “As a water engineering contractor, we have been familiar with similar structures for years, but the fact that so many technical aspects come together in a single project makes this assignment particularly interesting for us. I think I can speak for everyone in our company when I say this is a remarkable project for us,” concludes Gary Van Gulck.      

Een zakelijke vraag aan Herbosch-Kiere? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
  • CompanyHerbosch-Kiere
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.