First new bridge replaces railway embankment beside the Albert Canal in preparation for the Oosterweel Connection

During the extended Easter weekend, the first of four bridges will be slid into place on the railway lines between Luchtbal and Antwerp. As a result, Vaartkaai will be closed to traffic from Friday to Tuesday inclusive. The works are needed to prepare for the construction of the Canal Tunnels.
On 20, 21 and 22 April, rail traffic will not be possible on freight railway line 27A near the Albert Canal. Major works will be carried out on the railway embankments. Rail traffic will be diverted, causing limited disruption to freight transport.
Why are these works being carried out?
The work on the railway embankments is part of the preparatory works for the Oosterweel Connection. The Canal Tunnels will later be built beneath the railway embankments. They will connect the E19 from the north with the Oosterweel interchange to the west and Deurne to the east of the crossing with the Albert Canal. The tunnels will allow traffic to travel in both directions.
Read more about the Canal Tunnels >
The tunnels will be built using the cut-and-cover method. First, a large trench is excavated, then the tunnel is built at the bottom, before the space above it is filled in again. Excavating beneath the railway embankments would put their stability at risk. They are therefore already being partially replaced by railway bridges that can withstand the future excavation works.
What exactly is happening?
In recent months, a new concrete bridge approximately 60 metres long and weighing 3680 tonnes has been built right next to freight railway line 27A. During the Easter weekend, the tracks will be removed over the same distance, jacks will lift the new bridge and slide it into place where the tracks were removed. The tracks will then be laid on the new bridge. Tubular piles were installed in advance to support the new bridge. If everything goes according to plan, train services will resume without disruption on Tuesday morning.
The same works are scheduled for early and late June on the bridges on line 25 to the north and south, and on line 27A south of the Albert Canal. (see image) The bridges on line 12 will not be slid into place, but built on site. This railway line will consequently be out of service for six months at a later date.
Disruption
Freight traffic that would normally use line 27A will be diverted, causing limited disruption. Passenger services on the adjacent lines 12 and 25 will not be affected. Vaartkaai will be closed to all road traffic during the works. This also applies to the cycle path. A diversion via Campiniastraat and Groenendaallaan will be in place. The closure will run from Friday 19 April at 0u01 until Tuesday 23 April at 23u59.
Source: Oosterweelverbinding