Challenging foundation works for raising Theunisbrug successfully completed

Gedurende het hele traject ontfermde De Waal Solid Foundations zich over de volledige funderingswerken.
Gedurende het hele traject ontfermde De Waal Solid Foundations zich over de volledige funderingswerken.

The renewal of Gabriël Theunisbrug has entered its final stages. The two former bridges have been replaced by three new bridges: two for motor vehicles, cyclists and pedestrians, and one for trams.

For the foundation works, contractor Artes Roegiers, responsible for the civil engineering works on this project, called on De Waal Solid Foundations, a one-stop provider of retaining and foundation works.

Work on the new Theunisbrug over the Albert Canal, between Deurne and Merksem, has been in full swing since 2019. The old bridge has now been completely removed. The first two bridge sections were installed in their final position in October 2019 and opened to traffic in July 2020. In December 2020, the third and final section was also floated into its new position. Raising Gabriël Theunisbrug in Antwerp and widening the Albert Canal locally form part of the Albert Canal upgrade. This wider project involves removing bottlenecks that limit capacity on the Albert Canal. It is a collaboration between several partners, including De Vlaamse Waterweg nv, the Agentschap Wegen en Verkeer, Aquafin, De Lijn and the city of Antwerp.

Work on the new Theunisbrug over the Albert Canal, between Deurne and Merksem, has been in full swing since 2019.

Now that the bridge is in its final position, contractor Artes Roegiers is completing the new approach ramps, after which the new road surface will be laid. At the same time, work continues on rebuilding Carettebrug, which lies in line with the bridge. Its underpass is being widened to improve visibility for motorists and provide more space for cyclists and pedestrians. The bridge is due to open to traffic by mid-July 2021, when Theunisbrug will be operating at full capacity.

Bored piles and displacement piles

De Waal Solid Foundations was responsible for all the foundation works throughout the project. “It was a substantial project, consisting mainly of installing bored piles,” says Damien Sneyers, business unit manager, piles, at De Waal Solid Foundations. “Based on the specified loads, De Waal determined the pile system, diameter, length and reinforcement. For this project, we opted for piles with a diameter of 600 mm, installed to a depth of 25 m. This applied to most of the bridge. In addition, the new bridge sections were assembled alongside the bridge. We installed around 200 displacement screw piles to support the assembly and allow the bridge sections to be moved onto the pontoons.”

Flexibility

Projects of this kind are ideally suited to De Waal Soild Foundations, but that does not mean there were no challenges. The length of the piles and the fact that most had to be drilled at an angle were far from straightforward, requiring specialist expertise. Damien Sneyers says: “Another challenge arose when we suddenly realised that one of the bridge abutments was beneath a high-voltage power line. This meant we could not use our largest machine there. We therefore developed an alternative using displacement screw piles.”

Work on the new Theunisbrug over the Albert Canal, between Deurne and Merksem, has been in full swing since 2019.

The fact that the ‘problem’ was spotted late meant De Waal Solid Foundations had to act quickly. Damien Sneyers says: “It was a challenge to change the design and propose an alternative in such a short time. In the end, however, the alternative proved even more economical and very competitive in terms of price, making it a win-win situation. The client accepted the solution quickly. It is at times like these that De Waal Solid Foundations’ flexibility and experience come to the fore.”

De Waal Solid Foundations completed its work in mid-February. “In the end, the project went the way we like it to, even though the phasing was certainly not straightforward. But because we have an extensive fleet of machinery, we can respond very flexibly to complex schedules. That proved true once again here, and I am convinced the client appreciates it too. Ultimately, a satisfied client is what we want,” concludes Damien Sneyers.

Question about this story? Ask your question

Wie aan Theunisbrug werkte

  1. contractorArtes RoegiersMentioned in Work on new Theunis Bridge in full swing
  2. totaalaanbieder voor beschoeiings- en funderingswerkenDe Waal Solid FoundationsMentioned in Work on new Theunis Bridge in full swing

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectTheunisbrug
  • ThemeExtending the life of bridges and tunnels
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.