Work on new Theunis Bridge in full swing

On 7 February, Flemish Minister for Mobility Ben Weyts officially launched the preparatory works for the new Theunis Bridge, which connects Deurne and Merksem. The main works also got under way in April. The construction of Theunis Bridge is a key part of the further upgrading of the Albert Canal and improving traffic conditions in and around Antwerp. “Everything is going according to plan,” says Olivier Rens of De Waal Solid Foundations, a specialist in deep foundations.
Container transport on Flemish waterways is on the rise, and a large proportion of it passes along the Albert Canal. Around 40 million tonnes of goods are transported on the canal each year, equivalent to two million lorry journeys a year, or 8,000 fewer lorries on our roads every day. As the clearance beneath the existing bridges over the Albert Canal is too low, De Vlaamse Waterweg nv is pressing ahead with upgrading the canal. All the bridges are being raised in stages to 9.10 metres, and the width beneath them is also being increased.

Contractor Artes Roegiers called on De Waal Solid Foundations to carry out the foundation works. (Image: Toon Grobet)
Crucial link
Theunis Bridge is seen as a crucial link in the project. “The bridge connecting Deurne and Merksem is an important link, but at just 48 metres wide, the canal is at its narrowest here,” says ir. Chris Danckaerts, managing director of De Vlaamse Waterweg nv. “Changes to the bridge are therefore needed as part of the canal’s development. We are raising the new Theunis Bridge from 6.82 to 9.10 metres. Beneath the bridge, we are widening the canal to 90 metres.”
For the foundation works, contractor Artes Roegiers, responsible for the civil engineering in this project, called on De Waal Solid Foundations, a full-service provider of retaining and foundation works. “Based on the specified loads, De Waal determined the piling system, the diameter,
the length of the piles and the reinforcement,” says Olivier Rens. “There were also a number of challenges. The piles are 24 m long, and most have to be drilled at an angle, which is no easy task. Only a handful of companies can do this.”

The two existing bridges are being replaced by three. The two outer bridges will each have two lanes for road traffic, while the middle bridge will carry trams. (Image: ZJA Zwarts & Jansma Architecten)
Design optimisation
Alongside the bridge works, the junction of Frans de l’Arbrelaan and Minister Delbekelaan, named Duvelsplein, is also being redeveloped. The junction is being renewed with safe crossing points, wide cycle paths, a new tram platform and a spacious public square for sport and recreation. Rather than opting for a standard bridge, the project team chose a bespoke design for the new Theunis Bridge. The two existing bridges are being replaced by three. The two outer bridges will each have two lanes for road traffic, while the middle bridge will carry trams. Wide, segregated cycle paths and footpaths will run along both sides of the bridge.

“The piles are 24 m long, and most have to be drilled at an angle, which is no easy task.” (Image: De Waal Solid Foundations)
Careful phasing of the works will minimise disruption, and all cycle, road and tram traffic will be able to continue, except during two weekend diversions for tram services. Olivier Rens says: “The piles are currently being installed, and everything is going entirely according to plan. This is partly thanks to the thorough preparation. Optimising the design and using the right technique, taking account of the ground conditions and the loads to be carried, is crucial. These are De Waal’s strengths on projects like this.”
From April 2020, work on Theunis Bridge will be combined with the redevelopment of the junction. The new square will be completed at the same time as Theunis Bridge. If everything continues to go according to plan, the works will be completed by spring 2021.

The bridge connecting Deurne and Merksem is an important link, but at just 48 metres wide, the canal is at its narrowest here. (Image: Toon Grobet)
Question about this story? Ask your question
Wie aan Theunisbrug werkte
- contractorArtes RoegiersIn this story
- totaalaanbieder voor beschoeiings- en funderingswerkenDe Waal Solid FoundationsIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectTheunisbrug
- ThemeUsing and protecting the subsurface
- SubjectGeneral
- CompanyArtes Roegiers
- CompanyDe Waal Solid Foundations