Safer traffic situation in Mechelen thanks to two new steel bridges

At the end of September last year, main contractor Franki Construct began preparatory work on behalf of Infrabel to renew the railway bridge at Stationsberg in Muizen (Mechelen).
Almex Metaal was commissioned to build the new steel arch bridge, and is also working on the steel construction of the cycle and pedestrian bridge in the station area of Mechelen. “We are responsible for the entire construction and installation of the steel structure,” says managing director Gert Neelen.
The 100-year-old bridge at Stationsberg had reached the end of its service life and was clearly in need of replacement. Franki Construct expertly demolished the bridge, which will be replaced by a new steel arch bridge with wider, and therefore safer, cycle and pedestrian paths. Gert Neelen: “It is a bowstring bridge weighing 82 tonnes, with a span of around 35 m. The arch bridge will have a concrete deck and cast-on concrete cycle paths, providing more space for vulnerable road users.” The bridge is expected to open to traffic by the summer. Until then, pedestrians and cyclists can use a temporary bridge, while road traffic will be diverted.
The second project involves a cycle and pedestrian bridge over the Brusselse Steenweg. It forms part of the wider Mechelse Tangent project. “Here, a box girder bridge weighing over 120 tonnes was chosen,” explains Gert Neelen. “The bridge is 67 m long and has 1 central pier. We are carrying out this project on behalf of Franki Construct as well, which is responsible for all the civil engineering works. For both bridges, Almex Metaal is responsible for the entire construction of the steel structure, which will be installed on top of the bearings.”

Trial assembly
Almex Metaal fabricates the various bridge components in the largest sections possible. Gert Neelen: “We first carry out a full trial assembly in our workshop. After dismantling, the various components are transported to the site. The arch bridge at Stationsberg was fully reassembled next to the tracks and lifted into place over the railway during the weekend of 13 and 14 February, while the tracks were out of service. The cycle and pedestrian bridge over the Brusselse Steenweg will be transported to the site in three sections, then positioned and welded in place. Installation of the cycle and pedestrian bridge is scheduled for March.”
A challenging timeframe
As well as fabricating the steel structure, Almex Metaal is also responsible for its installation. Once the structure is in place, Franki Construct will take over again to build the concrete bridge deck. In terms of construction and installation, Almex Metaal faces a particular challenge with the tight turnaround for the arch bridge at Stationsberg. Gert Neelen: “The timeframe is indeed very tight. The bridge will be subject to heavy loads, so the quality requirements are very stringent. They always are, but heavy loading brings additional regulations and inspections into play. That is not in itself a difficulty, but it is time-consuming, making a six-month schedule very tight.”
Almex Metaal deliberately targets the mid-sized bridge segment. Gert Neelen: “By that, we mean bridges weighing under 1,000 tonnes. We do have a 1,500-tonne bridge project in the pipeline in Genk, but that is more of an exception. One of Almex Metaal’s strengths in this mid-sized segment is flexibility. We always look for the most efficient way to turn the client’s requirements into a product. Whatever the design, Almex Metaal finds the right production method. We also have a highly efficient quality department that monitors projects very closely. We make no compromises, either on aesthetics or on quality.”

New production site
Almex Metaal is also looking to the future, as shown by its substantial investment in a new production site in Hoogstraten last year. “And that is not all, because we have also bought the adjoining plot. We intend to expand our activities further. For now, our steel structures are transported elsewhere for preservation and painting. We want to bring that work in-house in the near future too. In 2022, we will therefore build a new production hall,” concludes Gert Neelen.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeExtending the life of bridges and tunnels
- SubjectRoad construction