Safe cycling past bridges and tunnels in Evergem

Cyclists will soon be able to enjoy safe, uninterrupted rides in Evergem. On behalf of De Werkvennootschap, Willemen Infra is building two new cycle bridges and three cycle tunnels over and under the R4-West, allowing cyclists to cross the ring road and the railway running alongside it safely, without having to cross paths with cars. Willemen Infra will complete the work in just one year.
The cycle bridges and tunnels are part of the R4WO project, through which the Flemish government aims to make the R4 around Ghent safer and improve traffic flow. While work on the turbo roundabout at the Euro-Silo interchange is progressing well, WIllemen Infra also started work on the next interchanges last summer. The Zandekenbrug is being built in Kluizen at the junction with Hoogstraat, while the Hultjenbrug is being built at the Ovaal in Wippelgem. Three new cycle tunnels are also being built beneath the Ovaal. The Zandekenbrug will provide a cycling route to and from the port area, while the Hultjenbrug will connect the cycling routes between the residential centres of Wippelgem and Doornzele. The bridges and tunnels will also provide convenient links to other nearby cycle paths, including the F40 and F401 cycle highways. “The three cycle tunnels will be completed by the end of February, and the two bridges will follow in the spring,” says Yves Henderick, Civil Engineering Coordinator at Willemen Infra.

A logistical challenge
Building the tunnels presents Willemen Infra with a major logistical challenge. Each tunnel will be slid into position over the course of a single weekend. “We build the reinforced concrete tunnel just in front of the location where it is to be slid into place, resting on a layer of plastic so that it can move freely,” explains Yves Henderick. “Just before the weekend, the tunnel is lifted and the sliding tracks are put in place. On Friday evening, we close the ring road to all traffic, then slide the tunnel into position so that through traffic can resume on Monday morning.”
Steel bridges
The steel cycle bridges will be installed in the spring, in close cooperation with the steel fabricator from Spain. Willemen Infra is meanwhile making all the preparations needed to ensure a smooth installation. “We are already well under way with concreting the abutments and piers. The positioning of the threaded rods is crucial: they need to be accurate to the millimetre, which calls for thorough preparation and high-quality execution. Once the concreting work is complete, the steel bridge can be assembled,” says Yves Henderick.

All the expertise under one roof
Willemen Infra has extensive experience with infrastructure projects of this kind, so the company has the technical expertise well in hand. The challenge here lies instead in the tight schedule. The bridges and tunnels must be ready for commissioning within a year, by this summer. “The weekends when the tunnels are slid into position require a great deal of preparation, and meticulous planning is crucial during the weekend itself. We have the necessary expertise, as well as the machinery and workforce, to bring a project of this scale to a successful conclusion,” says Yves Henderick. “This is also a particularly instructive project for us, because after the first tunnel and bridge we will know exactly how best to approach the next ones. That also makes the project interesting in terms of productivity.”
“One major advantage is that we handle all aspects of road construction in-house, from concrete work and civil engineering to waterproofing, asphalting and conventional roadworks. This is not only efficient for our own planning, but also benefits the client, who can be confident that we can deliver the project from start to finish,” concludes Yves Henderick.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ProjectR4WO
- ThemeFuture-proofing roads and railways
- SubjectRoad construction