N49 continues its transformation into a full-fledged motorway

N49 continues its transformation into a full-fledged motorway

The junction of the E34 and Stroomstraat in Assenede is almost a thing of the past. The bridge over the E34/N49 will be completed this spring, marking another step towards turning the N49 into a full-fledged motorway. Once the junction disappears, it will no longer be possible to join or leave the E34 here. Willemen Infra is responsible for the entire roadworks project, from start to finish.

The bridge in Assenede and the road leading up to it have one lane in each direction, with a segregated two-way cycle path on the east side. On the bridge, a safety barrier separates cyclists from motorised traffic. To compensate for the loss of the slip roads, the southern service road between Vaartstraat and Stroomstraat was widened and reconstructed for local traffic and public transport. The ‘old’ Stroomstraat now connects to the service roads at the site of the current junction. 

Willemen Infra

Once the junction disappears, it will no longer be possible to join or leave the E34 here.


Safer
The N49, known as the expressway between Antwerp and the coast, dates from the 1970s. To make the road safer and improve traffic flow, the Flemish government decided to upgrade it to a full-fledged motorway. Motorists, cyclists and pedestrians will therefore no longer have to cross the E34. For the construction of the bridge in Assenede, the Agency for Roads and Traffic called on Willemen Infra’s expertise. “Alongside reconstructing the southern service road, the first phase also involved raising the earth embankments, building the bridge piers and installing drainage sewers,” says Yves Henderick, project manager at Willemen Infra.

Willemen Infra

Alongside reconstructing the southern service road, the first phase also involved raising the earth embankments, building the bridge piers and installing drainage sewers.


Tight schedule
Willemen Infra says the project’s tight schedule and deadlines were its biggest challenge. Yves Henderick says: “Timing was crucial. It was also very important for us internally to avoid any delays. A large volume of earth had to be brought in, and the abutments, with precast piles beneath them, had to be built on top of it. It was therefore essential to carry out all the works continuously. Above all, we had to make sure the concrete work was completed by the end of 2018.”

‘Old-fashioned approach’
Precast concrete is now standard practice on major roadworks projects, and the bridge in Assenede was no exception. However, modern techniques were combined with a more traditional approach. “Precast concrete is used as much as possible these days, but we chose to form the filigree slabs between the precast beams the old-fashioned way, by shuttering them on site,” says Yves Henderick. “The fact that we can carry out every aspect of the roadworks ourselves is a major strength of Willemen Infra. That way, we have everything in our own hands, which makes it easier to stick to the tight schedule.”

Willemen Infra

Building the bridge in two sections, one for each carriageway, meant traffic could continue to travel in both directions on the E34, while the junction of Stroomstraat and the N49 remained open until after the winter.


Completion in May
Work in Assende started in March 2018. Building the bridge in two sections, one for each carriageway, meant traffic could continue to travel in both directions on the E34, while the junction of Stroomstraat and the N49 remained open until after the winter. The bridge could have been ready for use in February this year, but as no asphalt surface course can be laid before 1 March 2019, the project will be completed in May. “We are, of course, very pleased to have met the schedule,” concludes Yves Henderick.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of bridges and tunnels
  • SubjectRoad construction
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.