Modern mobility on a historic heritage bridge
Text Philippe Selke Beeld TMI

At the Tour & Taxis site, NMBS has begun the complete renovation of the Jubelfeestbrug. The architectural design and structural engineering contract was awarded to TM SEA+partners and Delta GC. The heritage features of this protected bridge will be preserved to the greatest possible extent, while improving safety and comfort for pedestrians and cyclists. An exceptional project for Walloon steelwork contractor TMI, characterised by close collaboration with main contractor Galère. Arnaud Tourny, Project Manager at TMI, takes a closer look at the specific challenges involved in a renovation and restoration project of this kind.
Galère is currently restoring the protected steel structure of the more than 120-year-old structure, having previously dismantled its concrete bridge deck. TMI’s contract covers the fabrication and installation of a new bridge deck, this time in steel. In each direction, it will include a carriageway for motorised traffic, a cycle lane and a footway, without widening the existing structure. Arnaud Tourny: “Installation of the new steel elements is scheduled to start on 1 September 2025 and will take 40 calendar days. We are currently in the midst of producing them at our workshops in Seilles. There are 29 sections, each weighing up to 18 tonnes. They are approximately 20 metres long and 3.70 metres wide, requiring exceptional transport and careful delivery planning. A 450-tonne crane will be used for the lifting work, with a symmetrical load to prevent shifting.”
The sections are divided into conventional rectangular sections and special sections with sloping sides, located at either end or alongside the two central expansion joints (and at the abutments). Given their technical complexity, these special components required thorough preliminary investigation before fabrication.

New bridge deck on the old structure
The main challenge, however, lies in the interaction between the existing steel structure and the new bridge deck, particularly at the 140 support points. These must be positioned to millimetre accuracy, taking into account the lines of rivets on the existing structure. Arnaud Tourny: “After the existing bridge deck was dismantled, the structure rose by 10 mm. Galère carried out a 3D scan, which will help us coordinate the positioning of the support points with the assistance of designer SEA+partners. We have also taken surveying measurements in our workshops to measure and correct distortions inherent in the fabrication process. In particular, angular distortion caused by the large number of welds on the gutters on the floor of each section.”

Imposing and sophisticated
The extremely large sections also take up an entire production hall. Given their dimensions, it is not possible to carry out a trial assembly of the bridge deck, but each section is presented alongside the next to ensure a perfect fit. Arnaud Tourny: “So far, we have used around 435 tonnes of steel. However, this large quantity does not preclude a certain technical and architectural refinement. A mock-up was presented to the client to agree on the appearance of the steel plate’s undulating shape at the ends of the sections. Parapets and lighting will also be integrated into the new bridge deck structure, along with accessories such as benches. The parapets are quite unusual, as half of the vertical bars are 2.75 metres high. Lighting will also be integrated into the parapets, while the footways, for which we have to provide the supporting structures, will be made of wood and fitted with benches.”
In a few months, the renovated Jubelfeestbrug will once again have its original appearance and green colour, and NMBS will hand it over to Brussel Mobiliteit, which will become its new owner and manager. TMI will then be able to proudly add this new Brussels reference to its extensive portfolio.
Question about this story? Ask your question
Who worked on it
Jubelfeestbrug in Brussel, renovation
- main contractorGalère
- Waalse staalconstructeurTMI
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJubelfeestbrug
- ThemeExtending the life of bridges and tunnels
- SubjectRoad construction
- CompanyGalère
- CompanyTMI
















