Road construction

Flexible formwork system and the right engineering

Met behulp van het veelzijdig VARIOKIT bekistingssysteem van PERI zijn 18 prefabelementen geleverd voor de brug over de Essche Stroom. Het beton zal in het werk gestort worden.
Met behulp van het veelzijdig VARIOKIT bekistingssysteem van PERI zijn 18 prefabelementen geleverd voor de brug over de Essche Stroom. Het beton zal in het werk gestort worden.

The old bridge over the Essche Stroom in the municipality of Haaren (North Brabant, the Netherlands) is being demolished and replaced by a new ‘white bridge’. Roel Schmidt, site manager at contractor Strukton Civiel Zuid, explains that PERI was brought in to help find the right formwork solution for the project.

After removing the old bridge, Strukton installed steel tubular piles as a temporary steel structure for the new bridge. “The PERI slab formwork is placed on this, and the new bridge is cast on top of it,” explains Roel Schmidt. “We know PERI from previous projects. As a major player in the formwork market, we asked them to help us find a suitable solution.” Theo Vereijken, project manager at PERI, adds: “There is very little room between the steel structure and the underside of the bridge, so the limited clearance for erecting and striking the formwork had to be taken into account. Strukton clearly set out what needed to be done, and we factored everything into the formwork engineering. That is what collaboration looks like when everyone has the best possible end result in mind.”

The pre-assembled formwork on the VARIOKIT system. Thanks to the effective collaboration between PERI and Strukton, an optimum result is achieved.

Versatile formwork system 

“Using our versatile VARIOKIT formwork system and working closely with the contractor, we delivered 18 complete prefabricated elements to the site, pre-assembled. This also helps keep the project moving.” Theo Vereijken explains that the pre-assembled elements were supplied to the correct radius to accommodate the camber in the bridge deck. “Our flexible VARIOKIT system makes it possible to build all kinds of structures. It is cost-effective and ideally suited to short-term projects. Expert engineering can resolve complex challenges.”

Fast and safe striking

“The success of a project like this depends on how it is carried out,” says Theo Vereijken. “Strukton has a few skilled workers on site who are handling the PERI materials well.” Roel Schmidt adds: “That is only possible thanks to PERI’s thorough preparation.” Once the PERI formwork system had been installed, the reinforcement work began and the edge forms were set up. The 110 cm-thick deck, incorporating prestressing, is then cast in situ using no less than 250 cubic metres of concrete. For striking the formwork, PERI used the VARIOKIT system to build a formwork striking trolley, so no one has to get between the steelwork and the pontoon. “The elements are struck using lowering devices, and the deck can be rolled out with the help of the striking trolley.” The new bridge, with a span of 34 m and a width of 6 m, once again fully complies with the latest standards and the current traffic class.      

Een zakelijke vraag aan PERI BeNeLux België? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of bridges and tunnels
  • SubjectRoad construction
  • CompanyPERI BeNeLux België
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.