Extensive dewatering for Knokke-Heist junction reconstruction

As part of the reconstruction of the junction of Kalvekeetdijk and Natiënlaan in Knokke-Heist, commissioned by Agentschap Wegen en Verkeer, a cycle tunnel and an underground roundabout are planned.
The reconstruction of the junction, a two-lane roundabout, is being led by TM Soetaert-Jan De Nul and is needed to improve road safety at this busy junction. G. Smeyers carried out extensive dewatering for the construction of the underground structures and the installation of the sewerage system.
Pedestrians and cyclists will be separated from road traffic by means of underpasses beneath the roundabout. The sewerage system in the adjoining streets is also being renewed as part of the junction redevelopment. The works extend for approximately 500 lm along Natiënlaan and approximately 300 lm along Kalvekeetdijk.
A special requirement for the dewatering was that the net abstraction rate must remain below 2,500 m³/day at all times. The contractor commissioned a hydrogeological study to size the dewatering system required and assess how best to meet this condition, taking into account the phasing of the works and the fairly tight schedule that had to be observed.
Return dewatering
G. Smeyers was asked to submit a quotation for the proposed design. This involved a dewatering system consisting entirely of deep wells, with the dewatering water returned via recharge wells, except for a flow of approximately 100 m³/h. Dewatering for the roundabout, down to 8 m below ground level, was to be carried out within a water-retaining cement-bentonite wall. Dewatering for the sewer works, down to 4 m below ground level, was to be carried out in open trenches. The works were to be completed in two phases.
Following an initial discussion of the quotation, G. Smeyers proposed an alternative method of execution. This alternative met the specified requirement and was considerably more cost-effective. The dewatering and recharge works were therefore awarded to G. Smeyers.

Deep wells
Dewatering for the roundabout is carried out using deep wells within the planned water-retaining cement-bentonite wall, with all the pumped water returned via deep recharge wells. Approximately 28 dewatering wells are drilled for the roundabout excavation and fitted with submersible pumps of suitable capacity and head. The pumped groundwater is conveyed through approximately 2,000 lm of mirror-welded PE 160 mm collector pipe to 40 deep recharge wells, which infiltrate all the pumped groundwater back into the subsurface.
Dewatering of the sewer trenches, approximately 1,600 lm, is carried out using horizontal drains connected to suction pumps. The pumps are switched on and off as required by the works. The dewatering water is pumped to a pumping station set up at the junction, then conveyed onwards to the nearby Rietveldader, where it is discharged.
Minimising disruption
The works officially start on 16 November 2020. However, drilling the recharge wells and laying the collector pipe could be carried out with little disruption to traffic and the surrounding area, and work on these elements began in early October. The recharge system has now been fully installed. Once the cement-bentonite wall has been constructed, dewatering for the roundabout can be carried out and started up. Installing the recharge system in advance has resulted in a significant time saving.
The Knokke project is an important reference for G. Smeyers. “Our creativity and expertise in all possible dewatering techniques, together with our study department’s know-how in designing dewatering systems using a 3D computer simulation model, enabled us to convince our client and its client to entrust us with the extensive dewatering and recharge works,” the company says. “With this project, G. Smeyers once again demonstrates that it is the right partner to assess and carry out complex dewatering projects and bring them to a successful conclusion, to the complete satisfaction of our clients and their clients.”
Een zakelijke vraag aan Smeyers nv? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUsing and protecting the subsurface
- SubjectRoad construction
- CompanySmeyers nv