Albertkanaal bridge upgrades continue to make good progress

The public-private partnership project to upgrade the bridges over the Albertkanaal, cluster 1, continues to make good progress. In 2019, two more new bridges were launched into place, at Eindhout (February) and Zutendaal (April). The temporary joint venture Via T Albert, comprising Franki Construct, Willemen Infra, Hye and Aelterman, is managing the works. In total, the JV will raise seven bridges between Herentals and Eigenbilzen. All the works are scheduled for completion in May 2020. “A deadline that still looks entirely achievable,” says Sven Somers, project director at Via T Albert Bouw.
With almost 40 million tonnes of goods transported each year, the Albertkanaal is Flanders’ most important waterway. Container traffic in particular has grown sharply over the past decade. As part of efforts to increase the capacity of the Albertkanaal, De Vlaamse Waterweg nv is investing in its further development. The current restrictions on navigational clearance and width beneath the bridges are a bottleneck for inland shipping on the Albertkanaal. Raising the bridges to provide a navigational clearance of 9.10 m will allow inland vessels carrying four tiers of containers to pass safely and smoothly.
De Vlaamse Waterweg and Via T Albert signed the contract for the public-private partnership project to upgrade the bridges over the Albertkanaal, cluster 1, on 1 September 2017. The two parties entered into a public-private partnership covering the design, construction and financing, as well as 30 years of maintenance, of seven bridges over the Albertkanaal. The project forms part of the programme to raise around 60 bridges over the Albertkanaal in total. It is in line with the Declaration of Tallinn, signed on 17 October 2013 by the European Commission, France, the Netherlands, and the Flemish and Walloon regions. This will increase the capacity of Flanders’ most important waterway by 25%.
Greisch, BM Engineering, Infrabo, TML and Omgeving are responsible for the main studies in their respective fields: steel structures, civil engineering, drainage and roads, minimising disruption, and integrated design quality.

The steel structure for the new bridge at Eindhout was prepared in a workshop and then assembled at a construction site alongside the Albertkanaal.
Recently launched into place
The project’s strong progress was once again demonstrated in recent months with the launch of the bridges at Ham, Eindhout and Zutendaal. Unlike the bridges at Eindhout and Zutendaal, the new bridge at Ham is being built in place above the canal. The arch was positioned over the weekend of 20 January 2019, and the metal arch bridge will be ready by the end of March 2019. The new bridge at Zutendaal was assembled at the construction site near the Ford Genk industrial zone and launched into place on Sunday 7 April.
The first bridge to be launched into place this year was the steel arch bridge at Eindhout. The steel structure for the new bridge was prepared in a workshop and then assembled at a construction site alongside the Albertkanaal. “The concrete deck has now also been poured at Eindhout, and the works around the bridge are nearing completion,” says Sven Somers. “The bridge is due to open in May 2019. Overall, the project is going very well. Cooperation is running smoothly and we are very pleased with the progress we are making.”

The concrete deck has now also been poured at Eindhout, and the works around the bridge are nearing completion.
Working together
The seven bridges being upgraded by Via T Albert are located at Eigenbilzen, Zutendaal, Stokrooie, Kwaadmechelen Zwartenhoek, Eindhout, Geel-Stelen and Herentals-Lier. They are all steel arch bridges of the same type. “Planning and ongoing consultation with stakeholders are crucial to this project, so that disruption is kept to a minimum,” says Sven Somers. “Works of this kind affect every type of traffic: shipping, cyclists, pedestrians, road traffic and rail traffic. We also work closely with utility network operators to relocate all kinds of cables and pipes. Given the tight schedule for renewing all the bridges on time, it is quite a balancing act.”

The bridge at Eindhout was launched into place in February.
Maintenance
The construction works are scheduled for completion in May 2020. Minimising disruption is a key priority. De Vlaamse Waterweg and Via T Albert consult with municipalities and stakeholders to coordinate the works and limit disruption. This focus continues into aftercare, as the JV is responsible for maintenance as well as design, construction and installation. “And that is for a period of thirty years. We have already provided a special maintenance gantry, which we will use to inspect and repaint the undersides of the bridges regularly. In this way, we aim to take as much of the burden as possible off De Vlaamse Waterweg,” concludes Sven Somers.
Question about this story? Ask your question
Wie aan Verhoging bruggen Albertkanaal – cluster 1 werkte
- steel constructionGreischIn this story
- civil engineeringBM EngineeringIn this story
- riolering- en wegenisInfraboIn this story
- minder hinderTMLIn this story
- integrale ontwerpkwaliteitOmgevingIn this story
- diepfunderingsspecialistDe Waal Solid FoundationsMentioned in Deep foundation specialist takes on every challenge
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVerhoging bruggen Albertkanaal – cluster 1
- ThemeExtending the life of bridges and tunnels
- SubjectRoad construction
- CompanyGreisch
- CompanyBM Engineering
- CompanyInfrabo
- CompanyTML
- CompanyOmgeving