Willemen Infra gives Antwerp International Airport a new runway in record time

Op 11 oktober asfalteerden Willemen Infra in één keer de toplaag en zonder naden.
Op 11 oktober asfalteerden Willemen Infra in één keer de toplaag en zonder naden.

Antwerp International Airport reopened on 26 October. Willemen Infra and Aertssen Group, commissioned by the Airport Development Company (LOM), carried out a complete renovation of the runway. New sewerage and drainage systems were also installed. As the airport has only one runway, the renovation had to be completed within a very short timeframe. “By combining the strengths of Willemen Infra North, East and West, we managed to complete the work perfectly,” says Gert De Boeck, project manager at Willemen Infra.

The airport in Deurne was closed for major infrastructure works from 19 September to 25 October.

The airport in Deurne was closed for major infrastructure works from 19 September to 25 October. The runway had not received any structural maintenance for more than 40 years. A thorough renovation was needed to ensure the continued safety of air traffic. The difference in level at the transition between the runway and the runway strip was also eliminated. Gert De Boeck says: “Working in a temporary joint venture with Aertssen Groep, Willemen Infra took charge of the works. The old asphalt was milled off, and the sewerage, covered channels and cabling were removed. Reconstruction then began straight away.”

Combining forces

Willemen Infra and Aertssen began milling the asphalt surfacing on 19 September. Then 25 excavators set to work breaking up the existing sewerage system. The runway received at least one new asphalt base layer, and up to three in some sections. The secondary lighting cabling for the runway was milled into these layers. On 11 October, Willemen Infra laid the entire surface course in one operation, without joints. Willemen Infra has 4 asphalt plants in Flanders: Brugge, Gent, Kieldrecht and Lummen. No fewer than 100 lorries delivered asphalt for the project from the plants in Kieldrecht, Lummen and Gent.

Gert De Boeck says: “Willemen Infra North, East and West joined forces to lay the surface course. This was another advantage, as the 45 m-wide runway had to be paved in a single operation, without joints. We lined up six pavers from the three branches to make this possible. Being able to draw on several asphalt plants is also a major benefit for the client. The asphalt mix also had to be identical, and we made sure it was. That is certainly not an everyday operation.”

Willemen Infra and Aertssen Group, commissioned by the Airport Development Company (LOM), carried out a complete renovation of the runway.

27,000 tonnes of asphalt

Finally, the runway lights were installed, 415 energy-efficient lamps were fitted, and the surface markings were applied. A test flight was carried out on the renovated runway. The runway measures 1,510 m by 45 m. The renovation required no fewer than 27,000 tonnes of asphalt. The runway was also fitted with a rainwater drainage system comprising covered channels and sewers that carry rainwater to a retention pond. Instead of being discharged into the sewerage system, rainwater is now released gradually into Boekenbergpark. A total of 4.5 km of sewerage and 3 km of covered channels were installed. The works will extend the runway’s service life by 20 years. Air traffic resumed on 26 October.

“The biggest challenges on this project were undoubtedly the time pressure and coordinating all the phases, which inevitably overlapped.”

A tight schedule

“The biggest challenges on this project were undoubtedly the time pressure and coordinating all the phases, which inevitably overlapped. For example, we were laying the asphalt base layers on the runway at the same time as installing channels and sewerage alongside it. The schedule had to be drawn up and monitored with great precision to ensure that the different activities did not impede one another. Space was also limited. Work was under way across the full 45 m width at all times. But it is precisely on projects like this, with so many challenges, that Willemen Infra can stand out,” concludes Gert De Boeck.     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectYearbook
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.