Willemen Infra completes runway 07L/25R renovation at Brussels Airport

Willemen Infra completes runway 07L/25R renovation at Brussels Airport

Renovation work on runway 07L/25R at Brussels Airport has been completed on schedule, with the runway due to return to service on Sunday 23 August at 6 am. Willemen Infra worked around the clock, 7 days a week, to minimise the runway closure and the impact of the works. A major renovation of this runway was necessary to ensure the safety of air traffic in the future. Willemen Infra, then still known as Aswebo, had already renewed the airport’s two other runways in 2015 and 2016. 

Willemen Infra

Renovation work on Brussels Airport’s main runway, runway 07L/25R, began on 13 July. “Thanks to thorough preparation with all stakeholders, the hard work of all the contractors and favourable weather conditions at crucial times, the works remained on schedule throughout,” says the Brussels Airport press release. This means the runway can return to service as planned.

More than 100,000 working hours were completed over 6 weeks, with around 400 people working on site each day. In total, around 1,000 people contributed to the project. The renovation will extend the runway’s service life by at least 15 years.

In totaal werd er ongeveer 1 miljoen kuub grond aangevuld.

The runway works were extensive. The upper asphalt layers were milled off and relaid across almost the entire runway surface (3.3km by 45m). The runway’s lighting system, including all cabling, was replaced. Where it had not already been done, the lighting was upgraded to energy-efficient LED lights. The drainage system was also relaid, with new channels and sewer pipes.

“Dat de terminal gedurende de werken operatief blijft, zorgt wel voor een mooie uitdaging.”

Other work was also carried out on the data network cabling and the lighting system poles. The grass areas were restored and relaid.

With 26.4 million passengers and 667,220 tonnes of freight handled annually, Brussels Airport is one of Europe’s most important airports. 74 airlines operate at the airport.

Photos © Brussels Airport Company

Key figures

Asphalt works

  • 270,000 m² of asphalt (± 40 football pitches), or 70,000 tonnes produced at 3 asphalt plants
  • At peak times: 8,000 tonnes laid in 12 hours, using 30 asphalt pavers and 100 lorries on the runway

Markings

  • 25,000 litres of paint

Lights

  • 2,000 runway and taxiway lights
  • 290 transformer pits
  • 320 km of cabling
  • 31 km of saw cuts
  • 10 km of trenches

Drainage

  • 7.4 km of drainage channels
  • 1.4 km of new sewer pipes

Project management

  • 35 people managing the site
  • 15,000 hours of preparation

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.