Tracking demolition waste mandatory for larger demolition projects

Tracking demolition waste mandatory for larger demolition projects

From summer 2022, waste tracking will be mandatory for larger demolition, renovation or dismantling projects. You can use Tracimat for this tracking. A demolition follow-up plan has been mandatory for larger projects for some time. But from 1 July, tracking will also be a mandatory requirement for larger demolition, renovation or dismantling projects for which an environmental permit is applied for.

When is a demolition follow-up plan mandatory? A demolition follow-up plan lists all the waste materials that will be generated during demolition. It must be drawn up for demolition, renovation or dismantling projects involving

  • non-residential buildings with a building volume of more than 1,000 cubic metres;
  • predominantly residential buildings with a building volume of more than 5,000 cubic metres, excluding single-family homes;
  • infrastructure works and infrastructure maintenance works involving more than 250 cubic metres of rubble. 

Under the new regulations, tracking will be mandatory from 1 July 2022 whenever a demolition follow-up plan is required.

Find out more?

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.