Schijnpoort footbridge makes it easier for pedestrians to reach Sportpaleis

Schijnpoort footbridge makes it easier for pedestrians to reach Sportpaleis

Anyone who has been to a concert at Sportpaleis or Lotto Arena will know it all too well: congestion, queues and traffic chaos at the nearby Schijnpoort junction always cause a great deal of stress. With the new footbridge, the City of Antwerp aims to separate pedestrians from motor traffic, making the site safer and more efficient. The contractors installed the bridge sections in early January, and all the work should be completed by the Easter holidays. “This means pedestrians can already reach Sportpaleis safely during the Oosterweel Link works, without having to cross the busy junctions,” says Maurits Van Hoorde, project manager at Franki Construct.

The Schijnpoort junction is currently a very busy traffic hub used by cars, public transport, cyclists and pedestrians. The footbridge over Schijnpoortweg allows vulnerable road users to cross safely to the event venues outside the ring road. The project will also improve access to the car park at Park Spoor Oost.

Improving liveability

The project is good news not only for event-goers. The area around Sportpaleis and Lobroekdok will undergo a transformation in the coming years with the creation of Ringpark Lobroekdok and Ringpark het Schijn, following the demolition of the Merksem motorway viaduct. New parks, space for sport and recreation, and attractive cycle and pedestrian links are expected to improve the liveability of the surrounding neighbourhoods. By building the crossing now, ahead of the Oosterweel works, the City of Antwerp is limiting traffic disruption and ensuring traffic can continue to flow smoothly along the Singel during the works.

bd-deel-2b_300dpi-kopieren

Maurits Van Hoorde: “The city gave us a 60-hour window, from Thursday to Sunday evening. Lifting operations like this are sensitive to weather conditions.”

The footbridge will therefore be in place before the Oosterweel project, which will already untangle some of the traffic congestion around Sportpaleis. Apart from the slip roads, all traffic will run through a tunnel or cutting, reducing the impact on the surrounding area. In their place will be a simple connection, with slip roads in both directions at Sportpaleis and at the water treatment plant. This will get traffic onto the motorway faster and reduce rat-running and lorry traffic in Deurne-Noord, Luchtbal and Merksem.

Cycle bridge

Once that work is complete, a new project will extend the footbridge over the motorway. Cyclists will be able to use the cycle bridge to continue safely along the Ringfietspad past Sportpaleis and as far as the new IJzerlaan cycle bridge over the Albert Canal. The footbridge and cycle bridge will then be linked at the city square by Sportpaleis. Cyclists will be able to reach ground level from the footbridge or cycle bridge via a ramp or two staircases.

Lifting operation in early January

Franki Construct is the contractor for the project and spent the past year working on the foundations and steel bridge sections. The company began the foundation work and construction of the abutment on the Spoor Oost side in October 2018. This was followed by the construction of the bridge piers on the side of the water treatment plant and Lobroekdok.

In early January, the company installed all the bridge sections for the future footbridge at Schijnpoort. The spectacular operation attracted a large crowd of onlookers. From Spoor Oost, they watched two large cranes, each with a lifting capacity of 500 tonnes, place the bridge sections on the piers. A team of around 40 people worked round the clock on this major operation.

“Junction reopened ahead of schedule”

“But it went more smoothly than expected,” says Maurits Van Hoorde. “The city gave us a 60-hour window, from Thursday to Sunday evening. That seemed like a tight schedule, and of course we always build in a safety margin. Lifting operations like this are sensitive to weather conditions. For example, in strong winds we would have had to stop the installation for a few hours. But the work went so smoothly that we were able to reopen the junction to traffic 24 hours ahead of schedule. That also takes good co-operation with the city services, of course. Overall, you could say the project went smoothly thanks to the good co-operation with the City of Antwerp.”

burg-gelegd-2_300dpi-kopieren

The footbridge over Schijnpoortweg allows vulnerable road users to cross safely to the event venues outside the ring road.

650 tonnes

Franki Construct also co-ordinated the project and outsourced the production of the bridge sections to steelwork contractor Almex. The company, based in Essen, specialises in civil engineering and supplies a wide range of metal structures for railway infrastructure, bridges and roads, and non-residential construction. Almex has worked on various projects for Franki and has also been working on the project in recent months at a site close to the Schijnpoort junction. Gert Neelen, owner of Almex: “We are responsible for all the components above the foundations. That means producing, assembling and carrying out the detailed engineering for six bridge sections, weighing 650 tonnes in total. We incorporated the footbridge lighting into the bridge balustrade. The traffic lights on Noordersingel at the junction with Schijnpoortweg are also integrated into the design. Now that the temporary assembly is complete, we still have to weld the sections together and install the parapets.”

Construction site beneath the bridge

Logistics posed a challenge for this project. The original plan to transport the sections by water proved unfeasible. “Initially, we planned to assemble the bridge in six sections and then bring them in by barge,” Neelen explains. “But the nearby quay at Lobroekdok could not accommodate that. An effluent culvert underground there made it impossible to unload the bridge using a telescopic crane or drive the structure off the barge. That was a setback, but together with our construction partners we found a good solution: a site beneath the ring road bridge nearby. We built the six sections there, then transported them to the nearby junction during the installation weekend.”    

Question about this story? Ask your question

Who worked on it

Passerelle Schijnpoort in Antwerpen

  1. contractorFranki Construct
  2. staalconstructeurAlmex

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPasserelle Schijnpoort
  • SubjectGeneral
  • CompanyFranki Construct
  • CompanyAlmex
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.