Replacement of existing high-voltage line between Drogenbos and Buizingen

Replacement of existing high-voltage line between Drogenbos and Buizingen

In spring, transmission system operator Elia began replacing the existing high-voltage line between Drogenbos and Buizingen. While the new pylons are being installed, main contractor Democo nv. is building two temporary high-voltage pylons. The dewatering works are being managed by G. Smeyers. “Our in-house engineering department designed a dewatering system and associated recharge system using a 3D computer simulation model we developed ourselves,” says managing director René Lambrechts.

The project involves replacing the existing 2x150kV line between the Drogenbos and Buizingen substations. All the existing pylons along the route are being replaced with similar infrastructure that meets the strict safety standards in force today. The current high-voltage line has reached the end of its service life, and Elia is replacing it to safeguard the reliability of the national grid and the safety of the public and infrastructure. The project is part of the Federal Development Plan 2015-2025, approved by the Minister of Energy. The total investment in this upgrade is approximately 8 million euros.

A total of twelve abstraction wells were planned, six for each excavation pit.

Main contractor Democo nv. is currently building two temporary high-voltage pylons on site. This requires excavating two pits measuring approximately 20 x 20 m to a depth of around 3.5 m below ground level. Preliminary ground investigations provided a clear picture of the local ground conditions. René Lambrechts: “The soil consists of settlement-prone alluvial clay down to a depth of 6.5 m. Between 6.5 and 8 m we find coarse sand, from 8 to 10 m coarse sand with gravel, and at a depth of 10 m we encounter rock. To establish the correct groundwater level, a number of observation wells were first drilled at the locations of the future excavation pits. Groundwater was found at a depth of 1.60 m below ground level.”

Recharge dewatering

Elia’s substation is right next to the Brussels–Halle railway line. On the other side of the site is an old, still-occupied house. “An initial dewatering study immediately showed that the proposed wellpoint system would cause unacceptable settlement both near the railway line and at the house,” explains René Lambrechts. “As a result, an additional requirement was imposed to offset the effects of dewatering near the railway line and the house with a recharge system.”

The abstraction wells convey the pumped water through approximately 350 m of collector pipes made from mirror-welded PE pipe to 17 recharge wells.

G. Smeyers designed the dewatering and recharge systems in-house. René Lambrechts: “Our in-house engineering department designed a dewatering system and associated recharge system using a 3D computer simulation model we developed ourselves. A total of twelve abstraction wells were planned, six for each excavation pit. The abstraction wells convey the pumped water through approximately 350 m of collector pipes made from mirror-welded PE pipe to 17 recharge wells, 12 along the railway line and 5 around the house to be protected. The abstraction wells are designed to pump the groundwater without aerating it, ensuring that the recharge system operates effectively.”

An in-house engineering department designed a dewatering system and associated recharge system
using a 3D computer simulation model developed in-house.

Dewatering technician

G. Smeyers is closely coordinating this complex project during construction. “The entire dewatering and recharge installation is monitored throughout the dewatering works by a specialist dewatering technician. The works had to be carried out within a live high-voltage substation. All G. Smeyers employees have completed AVIP training, enabling them to work inside the substation. This work at Elia’s Buizingen substation is an important reference for the company and will help ensure that its long-standing, successful collaboration with Democo nv. continues for many years to come.”  

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
  • CompanySmeyers nv
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.