MBG and STADSBADER CONTRACTORS have started building a 200,000 m³ refrigerated storage tank for TGE GAS ENGINEERING in the Port of Antwerp. The tank is a key component of INEOS Project ONE, the ethane cracker with the lowest carbon footprint in Europe. 

Almost ten years after successfully completing an ethylene tank for INEOS, TGE, MBG and STADSBADER CONTRACTORS are once again combining their expertise to build a new ethane tank with a capacity of 200,000 m3. 

Project ONE’s new ethane cracker sets a new industry benchmark, with a carbon footprint less than half that of the best comparable crackers in Europe. The plant also has the potential to evolve towards net zero, as it already uses hydrogen released as a by-product of the cracking process to meet its energy needs, and can increase this to 100% once sufficient external hydrogen becomes available. 

Both MBG and STADSBADER CONTRACTORS have extensive experience in tank construction, giving them the expertise needed to deliver this multidisciplinary project to exacting safety and sustainability requirements. The tank, measuring 95 metres in diameter and 50 metres in height, has walls 80 centimetres thick for optimum safety. It rests on 603 foundation piles, each 1 metre in diameter, and a floating base slab that rises 1.8 metres above ground level. 

“We are confident that, with our combined expertise and track record of strong collaboration, we will successfully complete this challenging project. We are delighted to support our industrial clients in their transition and help establish a new industry standard,” said Jan Folens, Executive Director of STADSBADER CONTRACTORS, and Luc Stuyck, General Director of MBG. 

Chris Cnudde, Area Project Manager for INEOS Project ONE, said: 

“Based on our successful collaboration at INEOS sites in Zwijndrecht (Belgium), Grangemouth (United Kingdom) and Rafnes (Norway), we are confident that TGE, a leading designer and builder of full-containment cryogenic tanks, will bring this project to a successful conclusion together with its local partners.” 

Work on the tank began on site in early April 2023. The entire Project ONE complex is scheduled for completion in April 2026. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.