Flemish Government gets New Lock Zeebrugge project back on track

Flemish Government gets New Lock Zeebrugge project back on track

Revised schedule, taskforce set up and 12 additional staff

Following the previously announced delay, the Flemish Government is taking measures to get the complex New Lock Zeebrugge project back on track. A taskforce has been set up, the schedule has been reviewed in consultation with all those involved, and 12 additional staff are being recruited to strengthen the project team. Information sessions for local residents will be held at the end of February. 

Lydia Peeters, Flemish Minister for Mobility & Public Works: “The project is now at a particularly complex but crucial stage. The project team is examining the various options for integrating the lock and new road into the surrounding area, while continuing to give priority to the area’s liveability. Before this puzzle can be put together, the individual pieces first need to be studied. This is very time-consuming, more so than the consultancy firms and our administrations had anticipated. That is why, following discussions between the consultancy firms, the administrations, the Flemish Government, port company MBZ and the City of Bruges, we have revised the schedule. To strengthen the project team, I will also recruit 7 additional people with specialist knowledge and skills within my administration.”

Layout option for lock and connecting road at Visart site to be announced in summer 2022

Under the new schedule, the preferred layout option is expected to be announced this summer. The Visart location has already been decided, but the layout option will determine exactly where the lock and the Nx connecting road will be built and what they will look like. An information session for local residents will also be held around the summer. The project team will then develop this layout option further into a draft project decision. The aim is to submit it to the Flemish Government before the end of the current legislative term.

A new taskforce has been set up to monitor progress against this schedule and take the necessary decisions. It includes representatives of the Flemish Government, the City of Bruges and port company MBZ, among others. The taskforce met for the first time at the end of January. In addition to the 7 additional staff at the Department of Mobility and Public Works, port company MBZ will recruit 5 additional FTEs to help make construction of the new lock possible.

Clarity

Dirk De fauw, Mayor of Bruges: “It is good news for the people of Zeebrugge that the layout option will be announced later this year. I have often been told that they want to know where they stand. The layout option will make this clear: people will know how the project will fit into the surrounding area. It will also show how liveability in Zeebrugge will be safeguarded during and after the works. In my role on the taskforce, I will also closely monitor the further development of the plans.”

Tom Hautekiet, CEO of MBZ, adds: “This new approach is also a positive sign for the port and the businesses operating there. The new sea lock is extremely important, not only for us, but also for local residents and nearby businesses. The agreements reached are a step in the right direction, which makes us cautiously optimistic. It will now be up to all of us to work together to achieve the targets set.”

Information sessions on 24 and 25 February

The impact of each option once the lock has been built has now been mapped out. To inform local residents, the project team is holding two information sessions on 24 and 25 February. A separate time slot has been set aside for retailers and businesses. More information will be available from tomorrow at www.nieuwesluiszeebrugge.be.

About the complex New Lock Zeebrugge project
Through the ‘complex New Lock Zeebrugge project’, the Flemish Government is preparing the port of Zeebrugge and its surrounding area for the future. The project has three pillars:

  • a second access to the outer harbour;
  • a new Nx connecting road to improve mobility;
  • improved infrastructure and facilities to safeguard liveability in Zeebrugge.

The project will have a major impact on the surrounding area. That is why a strong emphasis is being placed on collaboration, dialogue and up-to-date information.

All the latest information about the project is available at www.nieuwesluiszeebrugge.be.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSluis Zeebrugge
  • ThemeStrengthening waterways and coastlines
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.