Elia and Amprion commission ALEGrO, the first interconnector between Belgium and Germany

Elia and Amprion commission ALEGrO, the first interconnector between Belgium and Germany

On Monday 9 November, transmission system operators Elia and Amprion inaugurated the first electricity interconnector between Belgium and Germany.

  • Commercial operations are scheduled to start on 18 November 2020 (day-ahead market)
  • ALEGrO will strengthen security of supply in both countries and contribute to the integration of renewable energy

The event, which was also available to watch via livestream, took place at Aachen City Hall and was attended either in person or remotely by German Chancellor Angela Merkel, Belgian Prime Minister Alexander De Croo, Minister-President of North Rhine-Westphalia Armin Laschet and Belgian Minister of Energy Tinne Van der Straeten. The ALEGrO interconnector will enable the two countries to exchange an additional 1000 MW (1 GW) of electricity. Commercial operations are scheduled to start on 18 November 2020 (day-ahead) and 8 December (intraday).

ALEGrO interconnector

ALEGrO connects the networks operated by transmission system operators Elia (Belgium) and Amprion (Germany) and is an essential link in the development of an integrated European electricity system. The connection will have a transmission capacity of 1000 MW, equivalent to the amount of electricity consumed by a city with a population of 1 million. The interconnector offers several benefits: it strengthens security of supply for both countries, supports the energy transition by enabling better integration of renewable energy, helps bring prices closer together and makes the connected regions more economically attractive.

90 km of lines and two converter stations

The 90 km HVDC interconnector connects the converter stations in Lixhe (Belgium) and Oberzier (Germany). These two stations will convert the direct current (DC) used by the interconnector into alternating current (AC), which is used across 98% of the Belgian grid. Direct current enables large volumes of electricity to be transmitted over long distances in both directions.

10 years of cooperation

Despite the current COVID-19 pandemic, the original schedule was maintained. The project was completed on time thanks to the outstanding work of both network operators, who worked closely with the Belgian and German authorities and local and regional administrations. ALEGrO will therefore begin commercial operations later this year. As the HVDC interconnector will be integrated into the meshed AC grid, capacity for commercial operations will be released in stages. Initial capacity will be made available to the market on 18 November through the day-ahead allocation mechanism, followed by the intraday market on 8 December and, finally, long-term capacity in early 2021.

“Our success in the energy transition depends on expanding the grids quickly. The new electricity link between Belgium and Germany is important not only for our two countries, but also for electricity trading and system security throughout Europe. In this respect, today is a good day for the internal energy market.” Angela Merkel, Chancellor of Germany

“ALEGrO is an important catalyst for sustainable energy. As you all know, Germany and Belgium have made the same strategic choices for their energy production: phasing out nuclear power and fully supporting climate-neutral energy sources. ALEGrO is the literal link between these two strategies. The interconnector will enable wind power to be distributed more effectively, including at times of peak generation. This is particularly important for connecting our country with a region such as North Rhine-Westphalia, one of Germany’s leading wind power producers.” Alexander De Croo, Prime Minister of Belgium

“The rapid and smooth delivery of ALEGrO demonstrates the strength of European cooperation. With this connection, we are deepening cooperation on the European internal electricity market and can support each other in developing the energy system for the energy transition, together with our Belgian neighbours and friends.”, Armin Laschet, Minister-President of North Rhine-Westphalia

“We welcome this project because it prepares us for the future. A future characterised by new opportunities and a new vision for our different societies. A post-COVID era in which Europe, with the help of the Green Deal, will become the first climate-neutral continent by 2050. The ALEGrO project is an important step in developing a shared future for both countries. Ambitious climate policy goes hand in hand with the transition to a sustainable energy system, moving away from nuclear power and fully supporting climate-neutral energy sources. By taking control of our own energy policy, we are creating and shaping our shared future.”, Tinne Van der Straeten, Belgian Federal Minister of Energy

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.