Circuit Zolder reopens with brand-new asphalt surface

With its ten corners, including three chicanes, Circuit Zolder presents a four-kilometre challenge not only for racing drivers, but also for contractors. It was no less than fifteen years since the renowned circuit had last received a new asphalt surface, so the time had come to restore the race track to its former glory. Main contractor APK called on Topcon to carry out a full 3D survey of the circuit. The other parties involved in this special project also opted for Topcon products and service. Together, they delivered an outstanding result: Circuit Zolder is in better shape than ever!
David Vanderbeek, infrastructure manager at Circuit Zolder, explains why it was time to resurface the track: “A circuit’s asphalt needs to be renewed on average every ten to fifteen years. By that point, the road surface is still in very good condition by ‘normal’ standards, but speeds of 230 km/h are reached on this track. In such conditions, every crack and every uneven patch in the road has an enormous impact. By resurfacing the circuit, we wanted to improve not only safety but also the drivers’ comfort.”
ALL IN 3D
APK managed the works and brought in several partners. Top-Off was first to mill off the existing asphalt surface. Before the team got started, the existing conditions were surveyed. This was not done in the traditional way with a measuring staff, but with an IPS3, a mobile mapper from Topcon. “Topcon not only carried out the 3D survey of the circuit, but was also closely involved throughout the project. They really listened to our needs and made adjustments where necessary. We could rely on them right through to the final stages,” says APK, the main contractor for the project. Top-Off and Topcon are no strangers to each other. APK managed the works and brought in several partners. Their partnership has been highly successful for more than ten years. So the decision to mill this project in 3D as well was an easy one. Using Topcon’s SmoothRide system, key areas such as the chicanes were surveyed precisely in no time. This quickly showed how much asphalt needed to be removed and where the gradients needed to be improved to achieve the desired result. This meant the track could be milled faster and to millimetre accuracy. “We chose Topcon as our exclusive partner more than ten years ago. The successful collaboration at Circuit Zolder once again proves that we make a strong team,” says Top-Off, the contractor responsible for the milling work.
REAL-TIME MONITORING
After milling, APK installed the new kerbs and drainage channels, and then it was time for the new asphalt surface. This was laid by Grizaco. As with all famous circuits, the asphalt mix remains a closely guarded secret. The paving was monitored in real time using Pavelink. This was also used to manage asphalt transport scheduling, ensuring an optimal paving temperature. The rollers following the pavers were fitted with a Topcon GPS system, ensuring optimum asphalt compaction. This was a real advantage, as several pavers were working simultaneously. The rollers could therefore work in overlapping passes; the operators could see a colour-coded map showing the number of passes around the circuit, displayed live on all screens.
LINE MARKING WITH A ROBOT
Finally, Ultimated carried out the layout for the circuit’s line marking, an important element in high-speed races. A robot was used to plot the points and lines. Where GNSS coverage was insufficient, the robot was controlled using a Topcon total station to mark out the lines.
Een zakelijke vraag aan Top-Off NV? Get in touch
Who worked on Circuit Zolder
- main contractorAPKIn this story
- setting out for line markingUltimatedIn this story
- supplierShell BitumenMentioned in Zolder Circuit resurfaced with specially developed polymer-modified bitumen
- asphaltGrizacoMentioned in Zolder Circuit resurfaced with specially developed polymer-modified bitumen
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCircuit Zolder
- ThemeFuture-proofing roads and railways
- SubjectGeneral
- CompanyTopcon
- CompanyTop-Off NV
- CompanyAPK
- CompanyUltimated