CGK Group Gullegem wins Aquafin framework contract worth 3 million euros

Aquafin, responsible for treating 88% of all domestic wastewater in Flanders, has called on CGK Group of Gullegem to replace 20-year-old ferric chloride tanks across Flanders. Replacing more than 70 tanks represents an investment of over 3 million euros. This will provide around 3 new employees with a guaranteed 4 years of work.
CGK Group of Gullegem, a specialist in sustainable and innovative solutions for storing, treating and using chemicals and other (hazardous) liquids, has recently landed an impressive long-term contract worth 3 million euros, the largest in its history. Aquafin, which is responsible for collecting and treating wastewater across Flanders, is making this investment to replace its 20-year-old single-wall ferric chloride tanks with bunds with double-wall tanks. It has called on CGK Group of Gullegem to carry out the work.
Maarten Schueremans, Project Manager, Aquafin NV:
“Aquafin NV is now starting to renew a large batch of existing chemical storage tanks, as these tanks have reached the end of their 20-year service life and Aquafin must always comply with the applicable VLAREM legislation when storing hazardous products. Given the large number of tanks to be replaced, we decided to put the supply and installation of the new tanks out to tender through a new framework contract. This framework contract offers Aquafin NV several benefits: a single supplier with whom we can build a genuine partnership over several years, favourable pricing through increased volumes and standardisation, and efficiency during the design and implementation phases, …”
The contract covers the supply, installation and commissioning of double-wall ferric chloride tanks with dosing pump cabinets, as well as the removal of the existing dosing equipment. We are also responsible for recycling the old tanks. Among other things, we are exploring the possibility of reprocessing them into plastic road plates for our LODAX division.
The first tanks will be delivered next month. They are for Wommelgem, Nijlen and Deurne. More than 70 tanks will be replaced across Flanders in total.
Stijn Dely, Business Unit/Supply Chain Manager at CGK Group:
“The tanks and pump cabinet are fully assembled at our workshop in Gullegem. Our technicians will then dismantle the existing tank and install the new one on site. Connecting the pipework is also part of the job. We have allocated one week per tank for the complete changeover, so careful planning is essential. We are confident that everything will run smoothly, thanks to our employees’ expertise. This great contract will provide work for around 3 employees for 4 years and is an excellent foundation for the new production hall that we will put into operation after the summer of 2023.”
Maarten Schueremans:
“Our procurement department drew up this framework contract and put it out to tender in accordance with public procurement legislation. After evaluating the various bidders, CGK Group of Gullegem was selected as the compliant bidder offering the best proposal.
CGK is a familiar partner to Aquafin, and we are confident that together we will make this chemical tank project a success for all parties.”