A showcase for expertise in dewatering and recharge

A showcase for expertise in dewatering and recharge

On the Aalter Landegem section, the number of tracks on railway line 50 A, which links Brussels South with Ostend, is being increased from 2 to 4. This means major alterations are needed at Bellem stop (Aalter). These include a new pedestrian underpass, designated KW05, with access ramps providing direct access to the platforms. Several new culverts, including an ecological culvert, are also to be built beneath the new railway lines.

The works are being carried out for Infrabel and TUC RAIL by main contractor Van Laere of Burcht. G. Smeyers of Zandhoven has been appointed to carry out the dewatering works. The box section for the KW05 pedestrian underpass is being prefabricated in an open excavation. At the underpass, ground level is around +10,70 TAW. “The excavation and the jacking route had to be dewatered down to +6,16 TAW,” says René Lambrechts, managing director of Smeyers. “The groundwater level is at +8,50 TAW, so wellpoint dewatering is certainly necessary. Given the nature of the subsoil, the size of the excavation and the required drawdown, vertical wellpoints were chosen.”

dsc2538_300dpi-kopieren

Negative advice

However, part of the KW05 structure lies within a Habitats Directive and VEN area. René Lambrechts explains: “The plan was to return the pumped groundwater through an infiltration ditch in the nature area, thereby offsetting the groundwater drawdown caused by dewatering. A series of drip collectors arranged in a fan shape was also planned to mitigate the adverse effects of any potential drying out.”

However, when the dewatering permit application was submitted, the Agency for Nature and Forests (ANB) issued a negative opinion. This was a serious setback, as the planned dewatering works could not begin without a permit. “This put the schedule for the remaining works at considerable risk,” says René Lambrechts. “ANB could not accept the proposed solution of recharge through infiltration ditches, with additional drip collectors, and stipulated that the works had to be carried out inside a watertight cofferdam. This was not really feasible for the contractor or the client.”

dsc2539_300dpi-kopieren

Given the nature of the subsoil, the size of the excavation and the required drawdown, vertical wellpoints were chosen.

New abstraction wells

G. Smeyers was contacted to develop a solution. René Lambrechts explains: “The planned dewatering system, using vertical wellpoints to keep the excavations dry, was retained but extended with new abstraction wells, positioned along the boundary of the worksite and as far as possible from the nature area. This made it possible to pump the groundwater without aerating it and convey it to recharge wells positioned at the edge of the nature area. Using our own 3D model, we were able to demonstrate that no adverse effects were expected in the nature area. Following constructive discussions, the Agency for Nature and Forests was convinced that the proposed solution was sound.”

Meanwhile, the necessary preparations were made on site to schedule the dewatering and recharge works. Thanks to good cooperation with the municipality of Aalter and staff from the Department of Environment, the permit was granted immediately. Installation of the dewatering system began on 10 September 2019. With several teams working on the job, the system was operational six days later. G. Smeyers monitored the dewatering and recharge system from the outset using an online monitoring system.

dsc2534_300dpi-kopieren

Expertise

During the TLO, the weekend of 30 November and 1 December, the box section of the underpass was successfully jacked into place as planned. “This project is an important reference for G. Smeyers and excellent evidence of our extensive expertise in dewatering works in general, and dewatering with recharge in particular. This expertise is further strengthened by our in-house design department, which uses 3D modelling to design solutions for the most complex situations. The existing cooperation between G. Smeyers and contractor Van Laere will only grow stronger as a result,” concludes René Lambrechts.    

Een zakelijke vraag aan Smeyers nv? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
  • CompanySmeyers nv
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.