Roads can bring people closer together, both literally and figuratively. The new Nordøyvegen, the ‘Northern Islands Road’, is proof of that. This road will connect five islands to the mainland, bringing around 10,000 residents of different municipalities closer together.
In autumn 2018, ‘Statens vegvese’, the Norwegian Public Roads Administration, appointed Skanska as main contractor. The choice was no coincidence: thanks to Topcon’s MAGNET Project, Skanska submitted the best project implementation plan during the tender phase. Its price was also the most competitive. With MAGNET Project, Skanska managed to save no less than fifty million euros, and was able to start the project in early 2019 with complete confidence.
Tourist attraction
“Connecting the islands to the mainland will bring enormous benefits to the community,” says Marianne Næro, project manager at the Norwegian Public Roads Administration. “People here depend on ferries to travel to the mainland. Everyday life will be easier when residents can drive to the mainland toll-free whenever they want. Nordøyvegen will also give local businesses a boost and enable local people to work together on education, healthcare and other public services,” says Marianne Næro, who is convinced that the new connections will attract more tourists to the northern islands.

The ‘Northern Islands Road’ will connect five islands to the mainland, bringing around 10,000 residents of different municipalities closer together.
“The most challenging aspect of this project is excavating rock to create a stable base in the sea for the construction of a bridge,” says Mehdi Hosseini, project planner for Skanska. “The rock comes from three to four tunnels that we are currently working on. So all stages of the project are interconnected. If tunnel excavation is delayed, moving the rock will also be delayed. This in turn affects the schedule for the marine fill, and that delay will ultimately hold up the bridge construction team. In a way, excavating the rock is therefore the most critical stage.”
Everything mapped out with MAGNET Project
“The big question was: what type of software could help us plan the rock excavation?” says Hosseini. “Topcon’s MAGNET Project helped us map how much material would be generated by excavating the tunnels and how much material would be needed to fill specific sections of the seabed. The software was also useful for optimising the transport of the rock.”
Several activities at once
“We used MAGNET Project during the tender phase to understand the scale of the project, visualise the plans and check the overall design,” explains Gregorz Gucwa, deputy project manager at Skanska. “A major advantage is the ability to bring all the information together in one place. You can check what is happening at different locations each day and see how the various activities interact and progress.”
Nordøyvegen is due to be completed by May 2022. The brand-new roads, bridges and tunnels will then connect the five islands to the rest of the country. The spectacular project is sure to become a major attraction.