1,500-tonne bus and cycle tunnel moved into its final position

1,500-tonne bus and cycle tunnel moved into its final position

Between 4 and 7 April, Jan De Nul will slide a new cycle and bus tunnel into place in the station area of Kortrijk, on behalf of Wegen en Verkeer West-Vlaanderen.

In recent weeks, Jan De Nul built this 35-metre-long, 1,500-tonne prefabricated tunnel beside its final installation site. The sliding operation will take 8 hours.

The new bus and cycle tunnel will link the south side of the station with the city-centre side. Buses and cyclists will be able to pass through safely and without hindrance from car traffic.

8-hour sliding operation

Around midday on Easter Sunday, Jan De Nul will begin work on the tunnel. The ground beneath the tracks will be excavated, after which the tunnel will be jacked up and placed on rails. This will allow the 35-metre-long, 1,500-tonne tunnel to be slid into position. The sliding operation itself will take around 8 hours and will start on the morning of Tuesday 6 April. 

From Wednesday 7 April, Jan De Nul will backfill the excavation, allowing Infrabel to reinstate the tracks. From Monday 19 April, all trains will once again run over the renewed tracks and through the new cycle and bus tunnel. 

Jan De Nul will then connect the bus and cycle tunnel at both ends to the new underground car park beneath Conservatoriumplein on the north side and to an approach ramp on the south side. Work on the cycle and bus tunnel will be fully completed by the start of the summer holiday.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.