Speed and quality go hand in hand in terminal expansion

De Noordzee Terminal van PSA Antwerp, de grootste containerbehandelaar in der Haven van Antwerpen, werd onlangs met 14 ha uitgebreid.
De Noordzee Terminal van PSA Antwerp, de grootste containerbehandelaar in der Haven van Antwerpen, werd onlangs met 14 ha uitgebreid.

The Noordzee Terminal operated by PSA Antwerp, the largest container handler at the Port of Antwerp, was recently expanded by 14 ha. Colas Belgium was brought in to carry out, among other things, the earthworks, foundation works, drainage works and asphalting. This was right up the experienced contractor’s street, given its expertise in logistics infrastructure, but the project was certainly not without its challenges. “The short four-month construction period was no mean feat, but this project shows that speed and quality really can go hand in hand,” says Stephan Buelens, Department Director at Colas Belgium.

PSA Antwerp is part of PSA International, one of the world’s largest port groups, headquartered in Singapore. In Antwerp, PSA operates 3 container terminals: MPET at the Deurganck Dock, Europa Terminal and Noordzee Terminal. Colas Belgium played a major role in the expansion of the last of these. Since 1988, Colas Belgium has been part of the Colas Group, a world leader in the construction and maintenance of transport infrastructure. Its focus is on urban planning and the construction and maintenance of road, rail, airport, port, industrial and logistics infrastructure.

Colas Belgium was brought in to carry out, among other things, the earthworks, foundation works, drainage works and asphalting.

Expansion and renovation

The project for PSA Antwerp was therefore a perfect fit for Colas Belgium. Noordzee Terminal (Quay 913) is equipped to handle the world’s largest ships and needed additional container capacity. It was therefore decided to expand the storage area by 14 ha. Stephan Buelens: “The site is used to stack empty containers. Together with a number of other contractors, our brief was to expand the 14 ha logistics yard, including Megaports in & out. The existing quay platform, also covering an area of 14 ha, also needed to be renovated. This involved completely renewing the asphalt surface course, as well as part of the asphalt binder course.”

From start to finish

Colas Belgium was involved in the project from start to finish. Stephan Buelens: “Among other things, we graded 14 ha of land, installed 5,000 m of drainage, provided cable trenches, placed 140,000 tonnes of granite foundations, installed 700 linear metres of covered drainage channels and laid 75,000 tonnes of asphalt. All the work was completed in early July, well within the planned schedule. It was quite a challenge to complete such a large project within a four-month period. We started draining the site in early March, and the final asphalting work was carried out in the first week of July.”

It was vital to have the right teams ready to carry out the foundation, drainage and asphalting work …

Preparation was crucial

The project as a whole went smoothly. Stephan Buelens: “That was largely thanks to very detailed and intensive preparation. Given the short construction period, it was crucial to plan everything down to the last detail and leave nothing to chance. This is a project worth around 10 million that had to be completed in 4 months, so preparation and overall site management were crucial. It was vital to have the right teams ready to carry out the foundation, drainage and asphalting work … The day the environmental permit was issued was also the day we had to start work.”

Noordzee Terminal (Quay 913) is equipped to handle the world’s largest ships and needed additional container capacity.

Fast and high-quality

Thanks to rigorous internal quality monitoring, Colas Belgium was able to achieve an excellent end result. “With this project, Colas Belgium has shown that fast work can also be high-quality work. Preparing and carrying out projects of this size in the right way is certainly one of our strengths, as is our flexibility, which allows us to respond quickly to unforeseen obstacles. For example, different types of work that would normally be carried out one after another had to be done simultaneously. We also set out the working method we had agreed internally in an approach plan beforehand. We would also like to thank PSA for placing its trust in us. PSA also helped make this a pleasant and successful collaboration,” concludes Stephan Buelens.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectRoad construction
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.