Precision 3D milling lays the foundation for refurbished runway at Antwerp Airport

Antwerp Airport reopened on 26 October. Commissioned by the Luchthavenontwikkelingsmaatschappij (LOM), Willemen Infra and Aertssen Group carried out a complete renovation of the runway. Holgo, which specialises in asphalt milling and sweeping, was brought in to carry out the milling work. “The added value of 3D milling was particularly significant on this tightly scheduled project,” says René Prenen, site manager at Holgo.
The airport in Deurne was closed from 19 September to 25 October for major infrastructure works. The runway had not received any structural maintenance for more than 40 years. A thorough renovation was needed to ensure the continued safety of air traffic in the future. The difference in level at the transition between the runway and the runway strip was also eliminated.

3D milling
René Prenen: “Antwerp Airport’s runway was known as one of the bumpiest in Europe, so renovation was needed. As a completely new profile had to be created, 3D milling was the right technique for the job. With conventional depth milling, a certain amount is simply milled off the existing profile, without addressing the unevenness and subsidence in a structural way. 3D milling, on the other hand, allows you to create a new profile and produce a smooth, even surface.”
Holgo began milling the asphalt surface on 19 September. René Prenen: “A surveyor from Willemen Infra determined the profile to be achieved, and we then had to mill several centimetres below it. This is only possible with 3D-controlled milling, using a total station. The team from Topcon provided support on site. On Monday morning, 19 September, we brought 4 milling machines into the airport and immediately began milling on both sides of the route.”

Efficiency and accuracy
Speed, efficiency and accuracy were crucial to this project. The airport had to reopen on 26 October, just over a month after work began, so there was no time to lose. René Prenen: “The day Holgo started milling, Aertssen began earthworks in the same area to install the drainage channels. The different operations followed one another at an overlapping pace. It was therefore important to complete the milling as quickly as possible. We were finished a week later, having milled around 35,000 tonnes.”

A relationship built on trust
The airport works were a first for Holgo. “Depth milling is part of our everyday work and we had already tested 3D milling extensively, but this was our first major 3D milling project and it has already become an excellent reference project. We were able to guarantee quality and accuracy down to the millimetre, while meeting the tight deadline. That was partly thanks to Willemen Infra’s excellent planning and coordination. The removal of the milled material was also no easy task, given the quantity involved. Holgo’s flexibility is a major asset on projects like this, as is our constant focus on quality and our young fleet of machinery. We also place great importance on keeping communication direct and building a strong relationship of trust with the main contractor. That was certainly the case on this project,” concludes René Prenen.
Een zakelijke vraag aan HOLGO? Get in touch