Road construction

N49 increasingly taking shape as a motorway

Text Niels Rouvrois Beeld Stadsbader Group

De N49 moet een conflictvrije autosnelweg worden, met gescheiden rijstroken, een maximumsnelheid van 120 km/u en parallelwegen die het lokale verkeer van de hoofdweg halen.
De N49 moet een conflictvrije autosnelweg worden, met gescheiden rijstroken, een maximumsnelheid van 120 km/u en parallelwegen die het lokale verkeer van de hoofdweg halen.

The N49 is currently being upgraded from an expressway to a motorway through several sub-projects. Commissioned by Agentschap Wegen en Verkeer, Stadsbader Group is responsible for the section between Damme and the Leopold Canal. “A multifaceted project that allowed Stadsbader Group to combine almost every aspect of infrastructure and civil engineering works,” says Andy Degrauwe, regional manager for infrastructure in the north-west.

The ambition is clear: the N49 is to become a motorway with no at-grade conflicts. This means separate carriageways, a maximum speed limit of 120 km/h and parallel roads that keep local traffic off the main road. In addition, dangerous junctions are being removed and replaced by a tunnel that provides safe passage for both motor traffic and cyclists. “Two dangerous junctions have been eliminated, and a tunnel has been incorporated to allow traffic to cross safely from north to south,” explains Andy Degrauwe. “This not only improves the flow of motor traffic, but also provides safe passage for cyclists and other vulnerable road users.”

The sub-project near Damme and the Leopold Canal was carried out by a temporary joint venture (TV) between Stadsbader and Stadsbader Contractors. Andy Degrauwe says: “This project brings together our strengths to best effect, with vertical integration within Stadsbader Group playing a prominent role. We have all the in-house expertise required for the roadworks and excavations as well as the civil concrete works, giving us strong control over the entire process, from design and production through to delivery.”

The sub-project near Damme and the Leopold Canal was carried out by a temporary joint venture (TV) between Stadsbader and Stadsbader Contractors.

Programme and water management

The N49 works are co-funded by Europe, which has an impact on the very tight deadline. The entire route had to be ready by 30 September to open to traffic the following day. “Meeting the deadline was undoubtedly the biggest challenge, but we delivered on time,” says Andy Degrauwe. “The underlying road network, in other words everything apart from the motorway, opened on 18 July. We did everything we could to make the tunnel ready for cyclists before the construction holiday.”

Water management also plays an important role, alongside road safety. A large basin was excavated to store water, while the Verloren Kreek was renewed and straightened, with ecological paths for small animals incorporated into the culverts. This required the N49 to be rerouted and widened slightly. “Measures like these give the project a distinctly sustainable, forward-looking character,” explains Andy Degrauwe.

The N49 is being upgraded from an expressway to a motorway.

Strength in numbers, behind the scenes too

Almost every aspect of infrastructure and civil engineering is covered by this project. Andy Degrauwe says: “Roadworks, foundations, drainage, soil improvement and stabilisation, reinforced concrete for the roundabouts, as well as the construction of an excavation pit, sheet piling, earthworks and embankment construction, waterglass grouting, horizontal drainage and dewatering, to name just some of the civil engineering work. The fact that Stadsbader Group has all this expertise under one roof is, of course, a major added value for the client.”

The success of this project is not only visible on and alongside the N49. Behind the scenes, too, numerous support services within Stadsbader Group help ensure a project’s success. “With our own production sites for steel, asphalt and (precast) concrete, recycling of secondary raw materials, soil treatment and more, we aim to manage projects as effectively as possible and respond quickly when circumstances change. And let’s not forget our in-house dispatch team, which ensures the continuous supply of materials and resources. These people are crucial and show that we build ‘together’, as one big family,” concludes Andy Degrauwe.

Almost every aspect of infrastructure and civil engineering is covered by this project.

Question about this story? Ask your question

Wie aan N49 werkte

  1. onafhankelijke certificatie-instellingCOPROMentioned in From aggregates to safety barriers: independent quality assurance in practice
  2. clientAgentschap Wegen & Verkeer (AWV)Mentioned in From aggregates to safety barriers: independent quality assurance in practice
  3. tijdelijke verenigingStadsbader ContractorsIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectN49
  • SubjectRoad construction
  • CompanyStadsbader Contractors
Share this article

Advertisement

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.