Road construction

Innovative vertical infiltration solution for the Hoeilaart cycle superhighway

Text DYKA / Niels Rouvrois Beeld DYKA

De Terhulpsesteenweg wordt heraangelegd met een naastliggende fietsostrade.
De Terhulpsesteenweg wordt heraangelegd met een naastliggende fietsostrade.

Work on the ring road around Brussels is bringing a major focus on expanding and improving cycling infrastructure. This will make it easier and safer to cycle alongside and across the ring road. The works include the reconstruction of the Terhulpsesteenweg in Hoeilaart, including a cycle superhighway. The new cycle superhighway has been fitted with a V-flow drainage system from DYKA, a vertical infiltration solution that combines three functions in one: collecting, storing and infiltrating rainwater.

The Terhulpsesteenweg is currently very unsafe for cyclists. In many places there is no cycle path, or it is in poor condition. To improve the situation, the Terhulpsesteenweg is being reconstructed with an adjacent cycle superhighway. Drainage from the cycle superhighway is handled by DYKA’s V-flow system. A total of 76 infiltration piles with a diameter of 800 were installed for this project.

Using the V-flow infiltration system means the existing sewer can be retained, causing less disruption to the surrounding area.

V-flow: a complete solution

V-flow is a vertical infiltration solution that combines three functions in one: collecting, storing and infiltrating rainwater. The system addresses local waterlogging and rainwater management. V-flow can also be easily combined with other V-flow units or integrated without difficulty into an existing rainwater solution, as in Hoeilaart. 

Using the V-flow infiltration system means the existing sewer can be retained, causing less disruption to the surrounding area. All that is needed is to drill a hole where the system is to be installed. Contractors also benefit from significantly lower installation costs. In addition, the system operates independently of other facilities, which also reduces installation costs.

The new cycle superhighway has been fitted with a V-flow drainage system from DYKA, a vertical infiltration solution that combines three functions in one.

Infiltrating at greater depth

Another reason for choosing vertical infiltration in Hoeilaart was the presence of a poorly permeable loam layer in the topsoil. This makes it difficult for rainwater to infiltrate into the ground. The V-flow system allows rainwater to infiltrate into deeper soil layers that are more permeable.

A total of 76 infiltration piles with a diameter of 800 were installed for this project.

DYKA Service

“At DYKA, we do everything we can to set ourselves apart through our excellent service,” says Bram Vreys, Technical Sales Manager at DYKA. “We make sure our customers have a hassle-free experience, supporting them from the design stage through to installation. This was certainly the case in Hoeilaart, where we supplied a bespoke V-flow system that perfectly met the customer’s needs.” 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeSpace for water and green infrastructure