Road construction

F3 cycle link to airport still on track thanks to well-considered solutions

De langverwachte fietsverbinding tussen de F3 fietsostrade Brussel-Leuven en de luchthaven van Zaventem is bijna een feit.
De langverwachte fietsverbinding tussen de F3 fietsostrade Brussel-Leuven en de luchthaven van Zaventem is bijna een feit.

The long-awaited cycle link between the F3 Brussels-Leuven cycle highway and Zaventem Airport is almost complete. Main contractor Colas is in the final stages of the works and can already look back on a particularly successful project.

“Although the coronavirus pandemic meant we could not start until six months later than planned, we have still managed to meet the original completion schedule in broad terms,” says Joris Verbeiren, divisional director at Colas.

The new cycle link, a collaboration between the Flemish Region, the Province of Flemish Brabant, Brussels Airport Company nv and the municipality of Zaventem, runs mostly along the bed of a former railway line. At the eastern end, it connects to the F3 east of the junction of Martinusweg and Nossegemwegje. At the western end, the cycle link connects to a new project by the municipality of Zaventem. This project will improve the existing unpaved path along the wall of Zaventem cemetery, which then connects to Kerkhoflaan. Finally, at the northern end, the new cycle link connects to A201 Leopoldlaan near Heidestraat, giving cyclists access to the airport.

The sub-base was milled in situ.

The cycle infrastructure is being built with a comfortable 3.5 m-wide asphalt surface and lighting. This will allow employees and travellers to cycle safely and easily to and from the airport. Colas was brought in to build the foundations, pavement and linear elements for the final missing section between the airport and the F3. Joris Verbeiren says: “The contract was put out to tender in 2019, and the plan was to start by 1 April 2020 at the latest. But the coronavirus pandemic disrupted those plans, and in the end we could not start work until 1 September.”

Milling in situ

The unplanned delay immediately created another obstacle. Joris Verbeiren says: “In winter, the site earmarked for the cycle path is almost inaccessible because of excess water that does not drain into the ground, or drains too slowly. The shift to autumn meant we had to look for ways to speed up the project after all. We therefore decided to mill the sub-base, which was to consist of sand and crushed stone, in situ. This had two benefits. Firstly, we could get to work quickly on our own alignment. Secondly, it also brought environmental benefits, which are always a key priority for Colas, as it avoided transporting soil, sand and crushed stone to and from the site. Finally, we also had to take account of a particular type of rabbit living in the verges. The original plan was to use metal track mats on the cycle path verges, but that would have covered too many rabbit burrows. So this problem was also resolved.”

As well as the foundations, pavement and linear elements, Colas is also providing access to Zaventem sports centre. Joris Verbeiren says: “The sports centre is significantly higher, while the cycle highway passes its lowest point there. We are currently putting the finishing touches to a structure with retaining walls, so cyclists can reach the sports centre via a sloping ramp in the embankment. All that remains is to lay the cycle path’s surface course, but that will only be possible once the asphalt plants reopen. Once that happens, we can complete the project.”

The cycle infrastructure is being built with a comfortable 3.5 m-wide asphalt surface and lighting.

Looking ahead

By anticipating the ground conditions and potential problems during the winter months, Colas shows that it always plans ahead. “We also looked ahead some time ago when it came to cycle highways in general. Working with Colas Noord-Oost in Limburg and Wirtgen, we developed a slipform paver that can lay kerbs simultaneously on both sides of the cycle path. This naturally saves a great deal of time. Colas’s strength lies in always thinking in terms of solutions and meeting the client’s needs. We started this project six months late, but still managed to have it almost complete by the end of 2020,” concludes Joris Verbeiren.     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectRoad construction
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.