Bergwijk Bridge set to be moved into place soon

Franki Construct is momenteel druk bezig met de eindfase van de bouw van de nieuwe Bergwijkbrug in Merelbeke, over de Ringvaart ter hoogte van de Fraterstraat.
Franki Construct is momenteel druk bezig met de eindfase van de bouw van de nieuwe Bergwijkbrug in Merelbeke, over de Ringvaart ter hoogte van de Fraterstraat.

Franki Construct, part of Willemen Groep, is currently putting the finishing touches to the new Bergwijk Bridge in Merelbeke, over the Ringvaart near Fraterstraat.

“This is a project that fits us perfectly, but it certainly presents technical and logistical challenges,” says Xander De Pryck, project manager at Franki Construct, which is carrying out the entire project in a temporary joint venture (TM) with Herbosch-Kiere.

In 2017, the local authority of Merelbeke responded to a call for projects by the European Regional Development Fund (ERDF) to build bridges for cyclists. Bergwijk Bridge is heavily used by pedestrians, cyclists and motorists alike, and has increasingly caused mobility problems, including traffic jams on Fraterstraat and Guldensporenlaan and unsafe cycle crossings near the bridge. The 60-year-old bridge was due for replacement in any case and no longer met the requirements for the passage of modern vessels. 

There was not enough room on the existing bridge for footpaths, cycle paths and a carriageway for motor traffic. Cyclists often rode in the middle of the carriageway on the bridge to reach the cycle waiting area at the traffic lights on Guldensporenlaan. For years, there had been talk of building a cycle bridge alongside the existing one. On behalf of De Vlaamse Waterweg, Herbosch-Kiere and Franki Construct are working together in a temporary joint venture to build an entirely new bridge.

The bridge itself was built beside its permanent location on a substantial temporary support structure, with portal frames to allow road traffic and shipping to pass underneath.

Concrete works completed

“In short, Franki Construct is building the new Bergwijk Bridge with three traffic lanes and a cantilevered composite cycle path,” says Xander De Pryck. “We are also widening Guldensporenlaan, connecting the road network to the new bridge and extending the current cycle superhighway around Ghent. Herbosch-Kiere is responsible for demolishing the existing bridge, which took place in January, ed., and renewing the bank protection.”

The final work on the substructure is now under way, while the concrete work on the bridge itself was completed a month ago. Xander De Pryck: “By starting work on the bridge superstructure earlier and building it elsewhere, we were able to save time. That was also necessary to keep the road closure as short as possible. We are currently completing the final concrete and earthworks on the abutments and piers, and are well under way with the installation of the launching system that will be used to slide the bridge into its permanent position over the course of next month.”

“In short, Franki Construct is building the new Bergwijk Bridge with three traffic lanes and a cantilevered composite cycle path.”

A technical and logistical challenge

Overall, the TM has managed to keep to the schedule. Xander De Pryck: “In spring 2021, the site was forced to close for several weeks because foreign workers had to quarantine. This delayed our concrete work, but fortunately the impact on the long-term schedule was limited because we had started work on the bridge superstructure earlier and the existing bridge could still be demolished as planned.

This project is a perfect fit for Franki Construct. Xander De Pryck: “But the assignment did present some serious challenges. The bridge itself is technically demanding. It has a particularly high level of post-tensioning, which makes it very sensitive to the distribution of reaction forces and settlement at the supports. This means the sliding operation at the end of June will not be straightforward. The bridge will be lifted very carefully at the supports to ensure that the load is distributed correctly across the entire structure. Any imbalance in the force distribution would be detrimental to the bridge. Moving it is therefore more than ever a technical feat.”

A second challenge was logistical. “The location is certainly not straightforward for this assignment. Building a bridge over the R4 and the Ringvaart, both of which had to remain in service, is not an everyday job. The bridge itself was therefore built beside its permanent location on a substantial temporary support structure, with portal frames to allow road traffic and shipping to pass underneath. That is certainly not standard practice either. The conditions were somewhat unusual, but one of Franki Construct’s strengths is delivering high-quality, efficient work even in more difficult circumstances. I am convinced that this gives us an edge,” concludes Xander De Pryck.     

Een zakelijke vraag aan Herbosch-Kiere? Get in touch

Wie aan Bergwijkbrug werkte

  1. afbraak van de bestaande brugHerbosch-KiereIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBergwijkbrug
  • SubjectRoad construction
  • CompanyHerbosch-Kiere
Share this article

Follow Grond/Weg/Waterbouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.