43 worksites on Flemish motorways in 2025

In 2025, major roadworks will be carried out at 43 locations on motorways, with renewed focus on renovating bridges, viaducts and tunnels. Disruption will be minimised by scheduling the most disruptive phases of the works as far as possible at night or during weekends, and by keeping as many lanes open as possible.
Today, Flemish Minister for Mobility and Public Works Annick De Ridder announced the 43 motorway worksites planned for 2025 together with the clients, Agentschap Wegen en Verkeer (AWV), Lantis, De Werkvennootschap and Infrabel. The works represent a total investment of 914 million euros, excluding the costs of the Oosterweel works and two public-private partnerships*. At 20 locations, the work involves the renewal of bridges (12 locations) and tunnels (8 locations).
The press presentation took place today at the Beverentunnel worksite, where renovation work is in full swing.

Renewal of tunnels, bridges and road surfacing
Work on our main roads is needed to improve the safety and service life of our road infrastructure. With an average of no less than 63.4 million vehicle-kilometres travelled each working day, our motorways have to withstand a great deal. “This high traffic volume in Europe’s logistics heart, combined with ageing roads, bridges and tunnels, makes substantial investment essential,” says Minister De Ridder. “Our infrastructure keeps our region moving and our people working. It must be safe, but also resilient. I am also giving extra attention to port roads, to ensure these important logistics routes are ready for the future.”
Minimising disruption
Roadworks inevitably cause disruption. In 2025, the greatest disruption is expected at the following locations:
ANTWERP
- (Lantis) Antwerp Ring Road (R1): construction of the North & East bypass and modification of the Deurne interchange
- Antwerp Ring Road (R1) at Antwerpen-Oost: concrete repairs
- Antwerp Ring Road (R1 x A12) at the Antwerpen-Noord interchange: replacement of bridge joints
- A12: renovation of the roof of the Jan De Vostunnel (OV)
FLEMISH BRABANT
- E40 Heverlee: installation of a cycle bridge
- E40 Dilbeek: bridge replacement
- Sint-Stevens-Woluwe interchange: repair of rutting
- E19 Vilvoorde: repair of a noise barrier
EAST FLANDERS
- E40 Aalst: installation of noise-reducing asphalt
- E40 Drongen: bridge replacement
“To minimise disruption, we coordinate the timing of our works with other clients and partners, such as local authorities, mobility organisations and employers’ organisations. We avoid having major roadworks taking place at the same time in the same area, and diversion routes are assessed in advance to ensure they do not cause disruption,” explains Kathy Vandenmeersschaut, Director-General of AWV. “The most disruptive phases take place at quieter times, such as at night, during weekends and holiday periods, including the construction holiday. We also keep as many lanes open as possible, for example by carrying out bridge works from the hard shoulder. Our Traffic Centre makes a detailed assessment of the impact of each worksite and examines the effects on the surrounding area.”


Avoid surprises
In a new national campaign on radio, social media and billboards, AWV is urging people to find out about planned works in their area, not only on motorways but also on regional roads. Knowing where roadworks are taking place helps people avoid surprises and, if necessary, adjust their journeys. All the information about the works is available at wegenenverkeer.be.
Worksite safety a priority
Workers are on site around the clock. “Very strict measures are taken when setting up a worksite to improve safety in the work zone. We ask drivers to observe the speed limit and follow the traffic signs. Please take extra care when approaching a work zone,” the minister also urged today.
Download maps and information sheets with detailed information about each worksite here.
*Two long-term public-private projects by De Werkvennootschap, the Zaventem interchange and development of the R4, are not included in this figure.
Full renovation of the Beverentunnel, setting for the presentation of Major Works 2025
For the presentation of the major works planned for 2025, we travelled to the Beverentunnel (R2) in the Port of Antwerp area. This motorway tunnel has been undergoing a full renovation since summer 2024, and work is in full swing. The first bore, towards Ghent, is almost fully complete. From mid-March, work will move to the other tunnel bore, provided a series of safety tests are passed. AWV expects traffic to be able to travel through a fully renovated Beverentunnel by the end of October.


Question about this story? Ask your question
Wie aan Beverentunnel werkte
- contractors' consortium
EquansMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration - technische coördinatieSwecoMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- clientAgentschap Wegen en Verkeer (AWV)Mentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- contractors' consortiumBESIXMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- contractors' consortiumBESIX InfraMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- contractors' consortiumBESIX UnitecMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- contractors' consortiumSTADSBADERMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration
- contractors' consortiumSTADSBADER CONTRACTORSMentioned in Beverentunnel renovation: a model of safety, innovation, sustainability and collaboration